From: Paul R Horvath [morningstarks@juno.com]
Sent: Tuesday, February 10, 2004 3:09 PM
To: jwyatt@ci.lawrence.ks.us
Subject: 933 Accessory Building
Julie,
Good news, our meeting with Tom Costello was productive. Armed with the
drawings Malcom provided Tom was able to give us some concrete
alternatives to total disassembly. A very simplified explanation of what
was suggested is to put temporary supporting walls in, put temporary
supports on the second floor, remove the roof a section at a time, pour a
cap over the existing footer, install new sill plates, run new joists
floor to 2nd floor, in the process pull the building back together making
it a plumb as possible, and rebuild the roof. Tom has agreed to be an
ongoing consultant on the project. Obviously Tom's insight/approach was
quite different from the other contractors. I'm sorry I didn't have this
consultation month's ago, it may have saved us all from some issues.
We're ready to start work once we get the permits reissued/extended?
I look forward to hearing from you.
Paul R. Horvath
Morning Star Management