Public Works Dept. Engineering |
Memo
To: City Manager
From: Director of Public Works
cc: Alan Landis
Date: April 13, 2004
Re: Project 1-SR1-104(S) (KLINK)
Milling, Overlay and Pavement Marking Improvements
6th Street (U.S. 40/59 Hwy.) – From Frontier Road to Arkansas Street
Bids were taken April 13, 2004 on the subject project. The results are as follows:
Engineer’s Estimate $ 550,535.95
LRM Industries, Inc. $ 462,297.90
R. D. Johnson Excavating Company $ 495,022.05
We recommend awarding the contract to LRM Industries, Inc. in the amount of $462,297.90 provided the contractor can meet the terms established in the contract documents.
Charles F. Soules, P.E.