Alabama Street - 3rd St to approx 200 ft south
STREET, STORM SEWER, and WATERLINE IMPROVEMENTS
PROJECT NO. 
RESOLUTION NO. 
ESTIMATED COSTS:
Engineering (10%) $8,500.00
Construction
   Street, Storm Sewer $60,000.00
    Roundabout $0.00
    Waterline $10,000.00
Contingency (10%) $8,300.00
Inspection/Administration (3%) $2,349.00
Legal & Issuance Costs (2.5%) $1,957.50
Interest on Temporary Notes (5%) $3,915.00
Subtotal $95,021.50
Property Acquisition $0.00
 
Grand Total $95,021.50
MAXIMUM ASSESSMENTS:  $                                        95,000.00
East Side - 53.12%  $                                        50,464.00
West Side - 46.88%  $                                        44,536.00
Plate No. Property Owner Lot Number Front Footage % SQ FT Ass. Per Parcel ($)
Tract 1 EAST SIDE 170.00 53.12%
Lot 1, Blk 1  - U05502 Brian W Perkins 7,650  $             8,411.03
Lot 6, Blk 1 - U05507 Brian W Perkins 7,649  $             8,409.93
Lot 5, Blk 1 -U05506 Brian W Perkins 7,650  $             8,411.03
Lot 4, Blk 1 -U05505 Brian W Perkins 7,650  $             8,411.03
Lot 3, Blk 1 - U05504 Brian W Perkins 7,649  $             8,409.93
Lot 2, Blk 1 - U05503 Brian W Perkins 7,650  $             8,411.03
  45,898  $           50,464.00
WEST SIDE:
Tract 2- U05520A Medical Arts Bldg 150.00 46.88%  $           44,536.00
       