Public Works Dept.

Engineering

Memo

To:                City Manager

From:           Director of Public Works

cc:               Alan Landis

Date:            May 4, 2004           

Re:                Project 12-SR2-404(C)

                      2004 Overlay Program, Phase 1

                       

Bids were taken May 4, 2004 on the subject project.  The results are as follows:

          Engineer’s Estimate                                     $   666,611.70

          Asphalt Improvement Company                  $   496,403.05

          LRM Industries, Inc.                                       $   499,635.35

We recommend awarding the contract to Asphalt Improvement Company in the amount of $496,403.05 provided the contractor can meet the terms established in the contract documents.

 

 

 

           

 

___________________

Charles F. Soules, P.E.