Updated 
7/2/2004
2004 Projects List
 
    Location Project Description Estimated Funding Source
        Cost   and Status
Projects in Progress ( PO's were cut in 2003, projects will be completed by summer 2004)          
Projects  PO        
Manager Number        
John/ PW   Misc Parks Park sidewalk & trail repairs (2003 - Penny Construction) $50,000 216-PO Cut - 90% complete
Lynn   Indoor Aquatic Center Install UV system in Lap Pool $25,000 211 4080  - PO Cut - August install
PO's Cut using 2004 money          
Lynn   Outdoor Pool Replace fence around slide $4,249 212 - PO Cut - 90% complete
Crystal   Downtown Install additional water hydrants with water line replacement $6,000 212 - Utilities Dept- 50% complete
Mark   Clinton Park Design work for new Shelter $8,800 CDBG  PO Cut - Started
John     Holcom Park Resurface basketball & tennis courts  $11,082 216 - PO Cut 30% complete
John/ Rowan   Stonegate Park Install new sidewalk to access playground $14,035 216 - PO Cut 20% complete
Lynn / Tim   East Lawrence Center Replace Weight Equipment $4,973 216 - PO Cut - Ordered
John   South Park Center Replace HVAC system / ducts / vents (estimated at $28,000) $39,797 212 - PO Cut August install
John   Veterans Park Repair fence around tennis court $1,690 216 - PO Cut 50% complete
John   CLSC Replace roll-up door that was vandalized $2,300 212 - PO Cut - Ordered
Tim   Holcom Park Center Replace furniture in lobby $950 212 - Ordered
Lynn   Community Building Install new bumper blocks in parking lot west of building $1,470 216 - PO Cut - Ordered
Rowan   Stonegate Park Install new playground  $9,600 216 - PO Cut - Ordered
Mark   Misc Park & Cemetery Roads Continue annual chip & seal maintenance program on the park roads $11,300 212 - PO Requested
Rowan /Crystal   South Park Install fences in landscape beds - east side $4,291 216  - PO Requested
Rowan/Mark   South Park Install new tot playground (4way animal hop & Flippo) $2,998 Private donation -PO requested
Projects being Bid          
Gary/John   Dog Park Run city water from YSI to Dog Park area  $15,000 212
John   Veterans Park Replace fence around basketball court $4,390 212
John   Depot Repair sunken sidewalks at entrance $2,500 216- Line 6023
John   Watson / Constant Parks Repair sunken sidewalks along 6th street $2,500 216- Line 6023
John   South Park Repair park sidewalk off of Vermont $3,500 216- Line 6023
John   South Park Design & build new steps for gazebo $6,000 216- Line 6004
Rowan   South Park Install water taps for irrigation of west side of park $4,500 216 - Line 6014
Rowan   South Park Irrigation phases along the west side of Mass $10,000 216 - Line 6014
Crystal   South Park New landscape beds along the west side of Mas $2,000 216 - Line 4201
Rowan   South Park Install new park signs $7,000 Private donation (Sertoma Club??)
Rowan/Mark   South Park Install new tot playground ($7000 was donated, have spent some) $4,002 Private donation
Gary   Arboretum Extend ag lime trail on west side $2,000 Arboretum Fund
Crystal / Ken   Arboretum Plant labels $1,000 Arboretum Fund
Crystal / Ken   Arboretum Excavation & seeding $4,000 Arboretum Fund
Gary / Ken   Arboretum Pond filling pipe $4,000 Arboretum Fund
Crystal / Ken   Arboretum Plant material (replacements & new) $4,000 Arboretum Fund
Gary   Clinton Lake Softball Complex Replace infield material to reduce rain-out $10,000 216 Line 6017
Gary   Clinton Lake City Park Build adult soccer fields near Outlet Park $5,000 Private funding - Adult soccer club
Gary   Clinton Lake City Park Move gate and improve parking at bottom of hill Sesque Point $1,000 216 - Line 4209
Gary   Clinton Lake City Park Improve parking and install fence area -Mutt-Run Dog Park $1,200 216 - Line 4209
Crystal   Bowersock Park Relandscape Park $8,000 Private funding - Bower Sock Dam 
Lynn / Tim   Community Building Upgrade kitchen area $5,000 212
Tim   East Lawrence Center Replace lockers in locker room $2,500 212
Possible 2004 Projects ( Need 212 or other funding sources)          
1   Prairie Park Obtain land west of Mary's lake ????  
2   South Park Center Move main entry doors to south side of building  (Building Security Issue) $13,000  
3   Clinton Park Replace park restroom - Does Not meet ADA $82,000 CDBG funds were not approved
4   Outdoor Pool Replace open flume slide bed $78,000  
5   Holcom Park Center Repaint top half of gym $22,000  
6   South Park Center Replace windows  $15,000  
7   Pat Dawson Billing Nature Area Install additional gravel and drain tube to allow parking at gate $2,500  
8   Oak Hill Cemetery Survey and map new sections of Cemetery $5,000  
9   South Park Center Interior upgrades walls, electric, flooring $20,000  
10   Dad Perry Park (North) Overlay north parking lot (was patched in fall of 2001) $18,000  
11   Indoor Pool Replace up-lights in lap pool - (Poor Fixtures, can't keep them burning) $37,000  
12   Indoor Pool Replace up-lights in leisure pool - (Poor Fixtures, can't keep them burning) $32,000  
13   Green Meadows Park- Phase I Earthwork pond, berms & seed (high public demand to do something with this park) $40,000  
14   Oak Hill Cemetery Upgrade Maintenance Facility $50,000  
15   Holcom Park Center Replace floor in lobby & Bly Room $25,000  
16   Clinton Park Replace park shelter  $65,000 CDBG funds were not approved
17   Indoor Aquatic Center Move Chemtrol to location away from chlorine $2,990  
18   Holcom Park Center Convert old batting cages into water spray park $55,000  
19   Community Building Convert racquetball court to area for treadmills & cardio equipment $15,000  
      Total $577,490  
           
19   Arboretum - Phase III Benches (5 benches at $600) $3,000 Rotary Club is raising money
20   Arboretum - Phase III Drinking Fountain $2,000 Rotary Club is raising money
21   Arboretum - Phase III Deck / Gazebo $12,000 Rotary Club is raising money
22   Arboretum - Phase III Landscape around deck / gazebo $7,000 Rotary Club is raising money
23   Arboretum - Phase III Waterfall $10,000 Rotary Club is raising money
Future Projects          
    Future Projects      
    Broken Arrow Park Overlay parking lot $25,000  
    Broken Arrow Park Replace ball diamond light $60,000  
    Broken Arrow Park Mudjack concrete floor in shelter to correct drainage problem $6,000  
    Centennial Park Install retention ponds in main creek to control erosion of creek bed $15,000  
    Centennial Park Sidewalk along 9th Street $15,000  
    Centennial Park Install rubberized play surface under playground $15,000  
    Centennial Park Master plan development Phase IV (park lighting , trails, sport fields) $250,000  
    Clinton Park Make repair to retaining wall behind shelter $18,000 Possible CDBG Funding
    Clinton Park Playground Replacement $55,000 Possible CDBG Funding
    Clinton Park Sidewalks $56,000 Possible CDBG Funding
    Clinton Park Sidewalks $56,000 Possible CDBG Funding
    Clinton Lake City park Built multi-use Gym Facility $1,000,000  
    Clinton Lake City park Pond to reduce City water usage for irrigation of Golf Course & YSI $60,000  
    Clinton Lake City Park Develop Master Plan Phase I  $250,000  
    Clinton Lake City Park Develop Master Plan Phase II  $250,000  
    Clinton Lake City Park Develop Master Plan Phase III  $250,000  
    Clinton Lake City Park Develop Master Plan Phase IV  $500,000  
    Community Building Install new drain under slab in basement to stop water problem $20,000  
    "Dad" Perry Park (West) Install court lighting in park $20,000  
    "Dad" Perry Park (West) Resurface Basketball & Tennis Courts $5,000  
    "Dad" Perry Park (West) Installation of curb and gutter on west parking lot $20,000  
    Downtown Mounting stands for yearly art display $7,500  
    Downtown Upgrade landscape & irrigation in downtown parking lots & planters $5,000  
    Depot Garden Install new wrought iron garden gate $2,500  
    Eagle Bend Golf Course Additional irrigation, north rough #15, west rough #9 $5,000  
    Eagle Bend Golf Course Additional irrigation, rough between #2 & #4 $3,500  
    Eagle Bend Golf Course Additional irrigation, west rough #18, north rough #11 $4,000  
    Eagle Bend Golf Course Additional irrigation around greens #2, #11, #18, #5 $2,000  
    Eagle Bend Golf Course Cart path additions - #4 tee & green $1,200  
    Eagle Bend Golf Course Cart path additions - #5 green , #6 tee, #7 green $3,600  
    Eagle Bend Golf Course Cart path additions - #9 tee, #17 green $2,400  
    Eagle Bend Golf Course Cart path additions - widen #9 green to practice green by pro shop $5,000  
    Eagle Bend Golf Course Maintenance shop addition and equipment storage $20,000  
    Eagle Bend Golf Course Fountain in pond on #8 $4,500  
    Eagle Bend Golf Course Built new club house $350,000  
    East Lawrence Center Repair tile art work in front of building  $3,500  
    East Lawrence Center Install AC drive on HVAC unit $3,000  
    Green Meadows Park-Phase II Install water & electric service & trees & seed  $80,000  
    Green Meadows Park-Phase III Develop phase II of park $80,000  
    Hobbs Park Resurface Basketball Court $3,500 Possible CDBG Funding
    Hobbs Park Replace park restroom $70,000 Possible CDBG Funding
    Hobbs Park Upgrade ball diamond lights $60,000 Possible CDBG Funding
    Hobbs Park Upgrade ball diamond fences $15,000 Possible CDBG Funding
    Holcom Park Upgrade court lights $20,000  
    Holcom Park Install rubberized play surface under playground $15,000  
    Holcom Park Upgrade ball diamond poles & lights   $150,000  
    Holcom Sports Complex Upgrade infield material to reduce rain-outs and improve playability $20,000  
    Langston Hughes Rec Center Architectural and Engineering work  $250,000  
    Langston Hughes Rec Center Build Center  Estimated $5,000,000
    Lawrence Entry Sign (2) Highway 10 east of town,  highway 40 west of town $50,000  
    Lyons Park Sidewalk replacement along 7th street and Lincoln Street $15,000 CDBG funds have been requested
    Lyons Park Replace court lights $18,000  
    Lyons Park Overlay north parking lot and new sidewalks in park $50,000  
    Lyons Park Install curb & gutter in parking lots $25,000  
    Lyons Park Upgrade infield material to reduce rain-outs and improve playability $15,000  
    Lyons Park Regrade ball diamonds to improve drainage. Reseed or sod $30,000  
    Outdoor Pool Replace pumps for water slides $4,800  
    Oak Hill Cemetery Chip & Seal additional roads  $15,000  
    Peterson Road Park Install playground  $40,000  
    Peterson Road Park Install parking lot $50,000  
    Peterson Road Park Install picnic areas with lights & water $50,000  
    Peterson Road Park Phase III of park development $510,000  
    Peterson Road Park Phase IV of park development $510,000  
    Prairie Park / Nature Center Build additional storage facility for Nature Center $12,000  
    Prairie Park Install park and court lighting $30,000  
    Rail Trail Development Development of new trail north of 23rd street Phase I $30,000  
    Rail Trail Development Development of new trail north of 23rd street Phase II $50,000  
    South Park Install rubberized play surface under playground $20,000  
    South Park Install main sidewalk along wading pool to allow maint access $10,000  
    SLT Install 2 drinking fountains on trail & trees at benches $6,000  
    Water Spray Park Install a water spray park ( unknown location)  $250,000  
    Watson Park  Install rubberized play surface under playground $20,000  
    Stadium - Baseball Develop Stadium for 16-19 year olds (location unknown) $500,000  
    YSI Build additional full size soccer fields (2-4 fields) $200,000