Proposed Project Schedule
09/09/04
Lawrence Fire & Medical Station No. 5
Critical Dates |
Intermediate Dates |
Proposed Associated Work |
|
|
|
June 11, 2004 |
|
Schematic Design Compete |
June 14, 2004 (week of) |
|
Present SD Package to Owner |
|
|
|
July 31, 2004 |
|
Design Development Complete |
August 18, 2004 (week of) |
|
Present DD Package to Owner |
Dates Revised 09.09.04 |
|
|
|
|
|
September 23, 2004 |
|
50% Complete Construction Documents |
September 23, 2004 (week of) |
|
Present 50% CD Package to Owner |
|
|
|
October 14, 2004 |
|
Submit 80% Specification |
November 2, 2004 |
|
100% CD Complete for Quality Control |
November 2, 2004 (week of) |
|
Present 100% CD Package to Owner |
November 9, 2004 |
|
Drawings out to Bid |
December 1, 2004 |
|
Receive Bids |
December 14, 2004 |
|
Submit bid to be included on City Commission meeting on 21st. |
December 21, 2004 |
|
City Commission meeting to approve contract to build #5 |
|
|
|
|
|
|