Project 2005 2006 2007 2008 2009
   
Kaw WTP Supply Improvements 501,000  
Kaw WTP Piping Modifications 811,000  
Clinton WTP Expansion 2,920,000  
Clinton WTP High Service Improvements 473,000  
Waterline Rehab/Replacement Program 1,082,000  
Security Improvements 541,000  
Misc. Water System Improvements 1,082,000  
Total 2005 CIP project estimate $7,410,000  
   
   
Clinton WTP Expansion   5,259,000  
Clinton WTP High Service Improvements 492,000  
Clinton WTP High Service Pumps 326,000  
Waterline Rehab/Replacement Program 1,125,000  
Security Improvements 562,000  
Misc. Water System Improvements 1,125,000  
Total 2006 CIP project estimate   $8,889,000  
   
   
Bowersock Dam Maintenance & Imp.     1,170,000  
30" main -  Indiana, 5th to 8th St. 231,000  
36" main - Indiana, Kaw WTP to 5th St. 237,000  
West 6th Street Elevated Tank 1,685,000  
Repaint Clinton WTP Ground Storage Tanks 796,000  
Waterline Rehab/Replacement Program 1,170,000  
Security Improvements 585,000  
Misc. Water System Improvements 1,170,000  
Total 2007 CIP project estimate     $7,044,000  
   
   
Kaw WTP Replace 3 High Service Pumps       158,000  
Operations & Maintenance Building  1,139,000  
30" main - 8th St/Tennessee St/9th St 441,000  
30" main -  Indiana, 5th to 8th St. 721,000  
36" main - Indiana, Kaw WTP to 5th St. 739,000  
Waterline Rehab/Replacement Program 1,217,000  
Security Improvements 730,000  
Misc. Water System Improvements 1,217,000  
Total 2008 CIP project estimate       $6,362,000  
   
   
Operations & Maintenance Building          4,737,000
30" main - 8th St/Tennessee St/9th St 1,376,000
Waterline Rehab/Replacement Program 1,265,000
Misc. Water System Improvements 1,265,000
Kaw WTP - UV regs 523,000
Clinton WTP - UV regs 523,000
Total 2009 CIP project estimate         $9,689,000
   
   
   
Project primarily required to meet anticipated growth related requirements  
Project primarily required by EPA and KDHE requirements  
Project primarily required to improve system reliability or transmission capacity