CITY OF LAWRENCE | |||||||||
Project 67-CP21-104(C) | |||||||||
Alley, 8th Street to 9th Street, Vermont to
Kentucky Pavement Reconstruction |
|||||||||
BID TAB | |||||||||
Engineer's Estimate - $167,600.00 | |||||||||
Bid Date: December 14, 2004 | |||||||||
LRM Industries, Inc. | R. D. Johnson Excavating, Inc. | Graybeal Const., Co., Inc. | |||||||
ITEM | DESCRIPTION | UNIT | QUANTITY | UNIT PRICE | AMOUNT | UNIT PRICE | AMOUNT | UNIT PRICE | AMOUNT |
1 | Demolition of Existing Alley | L.S. | 1 | $ 17,000.00 | $ 17,000.00 | $ 10,500.00 | $ 10,500.00 | $ 16,435.00 | $ 16,435.00 |
2 | 8" Fiber Reinforced Portland Cement Concrete | S.Y. | 1,067 | $ 42.00 | $ 44,814.00 | $ 49.90 | $ 53,243.30 | $ 48.50 | $ 51,749.50 |
3 | AB-3 Backfill (3" Depth) | C.Y. | 89 | $ 75.00 | $ 6,675.00 | $ 30.00 | $ 2,670.00 | $ 33.75 | $ 3,003.75 |
4 | Asphalt Patching | TON | 100 | $ 60.00 | $ 6,000.00 | $ 65.00 | $ 6,500.00 | $ 65.00 | $ 6,500.00 |
5 | Seeding, Mulching and Fertilizing | L.S. | 1 | $ 250.00 | $ 250.00 | $ 1,500.00 | $ 1,500.00 | $ 1,500.00 | $ 1,500.00 |
6 | Traffic Control | L.S. | 1 | $ 2,485.00 | $ 2,485.00 | $ 3,500.00 | $ 3,500.00 | $ 1,695.00 | $ 1,695.00 |
TOTAL | $ 77,224.00 | $ 77,913.30 | $ 80,883.25 | ||||||