City of Lawrence
Public Works Department
MEMORANDUM
DATE: December 14, 2004
TO: Mike Wildgen
City Manager
FROM: Chuck Soules
Public Works
On December 14, 2004 the City of Lawrence opened proposals for the following:
Project 67-CP-21-104(C)
Alley, 8th Street to 9th Street, Vermont to Kentucky
Pavement Reconstruction
VENDOR |
TOTAL BID |
Engineer’s Estimate |
$167,600.00 |
LRM Industries, Inc. |
$ 77,224.00 |
R. D. Johnson Excavating, Inc. |
$ 77,913.30 |
Graybeal Construction Co., Inc. |
$ 80,883.25 |
Recommendation Action:
Approve bid from LRM Industries, Inc. for the Alley, 8th Street to 9th Street, Vermont to Kentucky Pavement Reconstruction, in the amount of $77,224.00, provided the contractor can meet the terms established in the contract documents.
Incentive Recommendation: The contract will include $400 per day for liquidated damages. This project does not typically cause substantial public inconvenience for prolonged periods of time. No recommendation for incentive. Working days for this project is 50.
Attachment
cc: Dave Corliss
Bobbie Walthall
Frank Reeb
Alan Landis
Tammy Bennett