Professional |
|
KASOLD DRIVE FROM
PETERSON ROAD TO THE KTA |
|
|
|
|
|
|
|
|
|
|
Engineering |
|
Summary of Findings and Evaluation of Geometric
Alternatives |
|
Consultants |
|
City Project # 36-CPI2-704(S) |
|
PEC04A45-03975 (tlc) |
|
Lawrence, Kansas |
|
10/28/2004 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Estimated |
Potential |
Adequate |
Adequate |
Speed |
Pedestrian |
Consistent |
Impact on |
Right |
|
|
DESIGN ALTERNATIVE |
Construction |
for |
Intersection |
Roadway |
Control |
Crossing |
w/ Corridor |
Utilities
in |
of Way |
|
|
|
Cost |
Landscaping |
Capacity |
Capacity |
Provisions |
Provisions |
to South |
Util. Easements |
Costs |
|
|
Alternate A |
|
|
|
|
|
|
|
|
|
|
|
Five 12' Lanes with no median |
|
|
|
|
|
|
|
|
|
|
|
Traditional Intersections |
$1,989,240.00
|
Low |
Yes |
Yes |
No |
No |
No |
Low |
Low |
|
|
Alternate B |
|
|
|
|
|
|
|
|
|
|
|
Four 11' Lanes with Grass |
|
|
|
|
|
|
|
|
|
|
|
Median - Traditional
Intersections |
$1,874,287.00
|
Moderate |
Yes |
Yes |
No |
No |
Yes |
Low |
Low |
|
|
Alternate C |
|
|
|
|
|
|
|
|
|
|
|
Four 11' Lanes with Grass
Median |
|
|
|
|
|
|
|
|
|
|
|
Double Lane Roundabout
Intersections |
$1,955,031.00
|
High |
Yes |
Yes |
Yes |
Yes |
Maybe |
High |
High |
|
|
Alternate D |
|
|
|
|
|
|
|
|
|
|
|
Two 12' Lanes with Grass
Median |
|
|
|
|
|
|
|
|
|
|
|
Single Lane Roundabout
Intersections |
$1,838,250.00
|
High |
Yes |
Yes*** |
Yes |
Yes |
No |
Moderate |
Moderate |
|
|
Alternate E |
|
|
|
|
|
|
|
|
|
|
|
Two 12' Lanes with Grass
Median |
|
|
|
|
|
|
|
|
|
|
|
Single Lane Roundabout
Intersections |
|
|
|
|
|
|
|
|
|
|
|
(Access to Tillerman and
Huntington Provided) |
$1,838,250.00
|
High |
Yes |
Yes*** |
Yes |
Yes |
No |
Moderate |
Moderate |
|
|
Alternate F |
|
|
No, will require |
|
|
|
|
|
|
|
|
Three 12' Lanes with no median |
|
|
signal at
Grand |
|
|
|
|
|
|
|
|
Traditional Intersections |
$1,653,570.00
|
Low - Moderate |
Vista in 2015 |
Yes*** |
No |
No |
No |
Low |
Low |
|
|
|
|
|
|
*** Roadway will provide
for 40 mph in Design Year 2025 but will have high density. |
|
|
|
|
Landscaping
in Median & Along Sidewalk Cost = $73,718.00 NOT INCLUDED IN PROJECT |
|
|
|
Sprinkler
Irrigation System Cost = $40,250.00
(Not included in Project) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|