CITY
OF LAWRENCE |
|
|
|
|
|
|
|
|
Project No.
28-CP8-604(BD) |
|
Lake Pointe Drive,
22nd Terrace to Clinton Parkway |
|
Street, Storm Sewer,
Roundabout Improvements |
|
Bid Date: March 18, 2005 |
|
Bid Tab |
|
Engineer's
Estimate: $859,071.05 |
|
|
LRM
Industries, Inc. |
D. F. Freeman |
Linaweaver Construction, Inc. |
ITEM |
DESCRIPTION |
UNIT |
QUANTITY |
UNIT PRICE |
AMOUNT |
UNIT PRICE |
AMOUNT |
UNIT PRICE |
AMOUNT |
|
LAKE
POINTE DRIVE IMPROVEMENTS - SECTION 1 |
|
|
|
|
|
|
|
$ - |
1 |
Clearing and Grubbing |
L.S. |
1 |
$
960.00 |
$ 960.00 |
$
5,000.00 |
$ 5,000.00 |
$
20,000.00 |
$ 20,000.00 |
2 |
Removal of
Existing Structures |
L.S. |
1 |
$
1.00 |
$ 1.00 |
$
12,650.00 |
$ 12,650.00 |
$
5,000.00 |
$ 5,000.00 |
3 |
Unclassified Excavation |
C.Y. |
2566 |
$
3.10 |
$ 7,954.60 |
$ 9.25 |
$ 23,735.50 |
$ 9.00 |
$ 23,094.00 |
4 |
Type B
Compaction (MR 90) |
C.Y. |
542 |
$
2.90 |
$ 1,571.80 |
$ 5.00 |
$ 2,710.00 |
$ 4.00 |
$ 2,168.00 |
5 |
9"
Fly Ash Stabilization |
S.Y. |
5430 |
$
3.40 |
$ 18,462.00 |
$ 3.22 |
$ 17,484.60 |
$ 4.50 |
$ 24,435.00 |
6 |
Asphalt
Surfacing (Surface Course) (BM-2) |
Ton |
555.2 |
$
39.00 |
$
21,652.80 |
$
39.96 |
$ 22,185.79 |
$
52.45 |
$
29,120.24 |
7 |
Asphalt
Surfacing (Base Course) (BM-2B) (50% Recycle) |
Ton |
2446.5 |
$
34.00 |
$ 83,181.00 |
$
32.94 |
$ 80,587.71 |
$
40.62 |
$ 99,376.83 |
8 |
6"
Concrete Entrance (Reinforced) (A.E.) |
S.Y. |
160.6 |
$
36.00 |
$ 5,781.60 |
$
58.25 |
$ 9,354.95 |
$
38.00 |
$ 6,102.80 |
9 |
Concrete
Curb and Gutter (A.E.) |
L.F. |
2449.4 |
$
12.00 |
$
29,392.80 |
$
10.30 |
$ 25,228.82 |
$ 9.35 |
$ 22,901.89 |
10 |
6"
Asphalt Curb |
L.F. |
334.7 |
$
5.00 |
$ 1,673.50 |
$
10.80 |
$ 3,614.76 |
$
13.50 |
$ 4,518.45 |
11 |
Concrete
Sidewalk (4") (A.E.) |
S.Y. |
1330.5 |
$
19.00 |
$ 25,279.50 |
$
21.65 |
$ 28,805.33 |
$
31.00 |
$ 41,245.50 |
12 |
5'
Access Ramp |
Each |
2 |
$
1,000.00 |
$ 2,000.00 |
$
1,350.00 |
$ 2,700.00 |
$
1,100.00 |
$ 2,200.00 |
13 |
5'
x 4' Standard Curb Inlet (Precast) |
Each |
1 |
$
2,900.00 |
$ 2,900.00 |
$
2,916.00 |
$ 2,916.00 |
$
2,500.00 |
$ 2,500.00 |
14 |
5'
x 5' Standard Curb Inlet (Precast) |
Each |
1 |
$
3,230.00 |
$ 3,230.00 |
$
3,240.00 |
$ 3,240.00 |
$
2,800.00 |
$ 2,800.00 |
15 |
6'
x 4' Standard Curb Inlet (Precast) |
Each |
2 |
$
3,230.00 |
$ 6,460.00 |
$
3,240.00 |
$ 6,480.00 |
$
2,700.00 |
$ 5,400.00 |
16 |
8' x 4' Standard Curb Inlet
(Precast) |
Each |
1 |
$
3,550.00 |
$ 3,550.00 |
$
3,564.00 |
$ 3,564.00 |
$
3,200.00 |
$ 3,200.00 |
17 |
5' x 5'
Junction Box (Precast) |
Each |
1 |
$
3,550.00 |
$ 3,550.00 |
$
3,564.00 |
$ 3,564.00 |
$
3,300.00 |
$ 3,300.00 |
18 |
18"
Storm Sewer (CMP) |
L.F. |
342 |
$
52.00 |
$ 17,784.00 |
$
51.84 |
$ 17,729.28 |
$
55.00 |
$ 18,810.00 |
19 |
30"
Storm Sewer (CMP) |
L.F. |
390 |
$
66.00 |
$ 25,740.00 |
$
65.88 |
$
25,693.20 |
$
70.00 |
$ 27,300.00 |
20 |
36" Storm Sewer (CMP) |
L.F. |
20 |
$
94.00 |
$ 1,880.00 |
$
93.96 |
$ 1,879.20 |
$
86.00 |
$ 1,720.00 |
21 |
Flowable Fill |
L.F. |
476 |
$
56.00 |
$ 26,656.00 |
$
60.48 |
$ 28,788.48 |
$
80.00 |
$ 38,080.00 |
22 |
Traffic
Sign (Installed) |
Each |
1 |
$
650.00 |
$ 650.00 |
$
648.00 |
$ 648.00 |
$
660.00 |
$ 660.00 |
23 |
Silt
Fence |
L.F. |
1565 |
$
1.50 |
$ 2,347.50 |
$ 2.75 |
$ 4,303.75 |
$ 2.00 |
$ 3,130.00 |
24 |
Temporary
Curb Inlet Sediment Barrier |
Each |
5 |
$
100.00 |
$ 500.00 |
$
110.00 |
$ 550.00 |
$
150.00 |
$ 750.00 |
25 |
Temporary
Seeding |
L.S. |
1 |
$
880.00 |
$ 880.00 |
$
2,700.00 |
$ 2,700.00 |
$
4,000.00 |
$ 4,000.00 |
26 |
Construction
Staking |
L.S. |
1 |
$
2,700.00 |
$ 2,700.00 |
$
5,551.20 |
$ 5,551.20 |
$
3,550.00 |
$ 3,550.00 |
27 |
Seeding,
Fertilizing and Mulching |
L.S. |
1 |
$
1,400.00 |
$ 1,400.00 |
$
2,700.00 |
$ 2,700.00 |
$
6,000.00 |
$ 6,000.00 |
28 |
Mobilization |
L.S. |
1 |
$
8,040.00 |
$ 8,040.00 |
$
19,260.01 |
$ 19,260.01 |
$
20,000.00 |
$ 20,000.00 |
|
TOTAL SECTION 1 |
|
|
|
$ 306,178.10 |
|
$ 363,624.58 |
|
$ 421,362.71 |
|
CLINTON
PARKWAY AND LAKE POINTE DRIVE - INTERSECTION IMPROVEMENTS - SECTION 2 |
|
|
|
|
|
1 |
Clearing and Grubbing |
L.S. |
1 |
$
960.00 |
$ 960.00 |
$
5,000.00 |
$ 5,000.00 |
$
4,000.00 |
$ 4,000.00 |
2 |
Removal of
Existing Structures |
L.S. |
1 |
$
25,900.00 |
$ 25,900.00 |
$
35,000.00 |
$ 35,000.00 |
$
30,000.00 |
$ 30,000.00 |
3 |
Unclassified Excavation |
C.Y. |
2095 |
$
3.10 |
$ 6,494.50 |
$ 7.50 |
$ 15,712.50 |
$
15.00 |
$ 31,425.00 |
4 |
Type B
Compaction (MR 90) |
C.Y. |
877 |
$
2.90 |
$ 2,543.30 |
$ 5.00 |
$ 4,385.00 |
$ 4.00 |
$ 3,508.00 |
5 |
6"
AB-3 Base |
S.Y. |
367 |
$
5.00 |
$ 1,835.00 |
$ 6.90 |
$ 2,532.30 |
$ 5.00 |
$ 1,835.00 |
6 |
9"
Fly Ash Stabilization |
S.Y. |
3723.5 |
$
3.40 |
$ 12,659.90 |
$ 3.15 |
$ 11,729.03 |
$ 4.50 |
$ 16,755.75 |
7 |
10"
Concrete Pavement (NRDJ) (A.E.) |
S.Y. |
2777 |
$
59.10 |
$ 164,120.70 |
$
63.25 |
$ 175,645.25 |
$
60.00 |
$ 166,620.00 |
8 |
8"
Exposed Aggregate Concrete (Reinforced) (A.E.) |
S.Y. |
287 |
$
67.30 |
$ 19,315.10 |
$
81.40 |
$ 23,361.80 |
$
76.45 |
$ 21,941.15 |
9 |
6"
Exposed Aggregate Concrete (A.E.) |
S.Y. |
80.3 |
$
63.00 |
$ 5,058.90 |
$
72.60 |
$ 5,829.78 |
$
68.00 |
$ 5,460.40 |
10 |
Concrete
Curb and Gutter (A.E.) |
L.F. |
2783.3 |
$
15.00 |
$ 41,749.50 |
$
18.68 |
$ 51,992.04 |
$
17.00 |
$ 47,316.10 |
11 |
8"
Concrete Protection Curb (A.E.) |
L.F. |
183.8 |
$
17.00 |
$ 3,124.60 |
$
27.15 |
$ 4,990.17 |
$
33.00 |
$ 6,065.40 |
12 |
10' Fiber Reinforced Concrete
Recreational Path (6")(A.E.) |
S.Y. |
552.9 |
$
59.00 |
$ 32,621.10 |
$
43.55 |
$
24,078.80 |
$
34.00 |
$ 18,798.60 |
13 |
5' Concrete
Sidewalk (4")(A.E.) |
S.Y. |
72.2 |
$
18.00 |
$ 1,299.60 |
$
21.63 |
$ 1,561.69 |
$
31.00 |
$ 2,238.20 |
14 |
10'
Access Ramp |
Each |
6 |
$
1,350.00 |
$ 8,100.00 |
$
1,525.00 |
$ 9,150.00 |
$
1,100.00 |
$ 6,600.00 |
15 |
Median
Ramp Crossing |
Each |
3 |
$
1,610.00 |
$ 4,830.00 |
$
2,025.00 |
$ 6,075.00 |
$
2,750.00 |
$ 8,250.00 |
16 |
5' x 4' Standard Curb Inlet
(Precast) |
Each |
2 |
$
2,380.00 |
$ 4,760.00 |
$
3,240.00 |
$ 6,480.00 |
$
2,500.00 |
$ 5,000.00 |
17 |
12" Storm
Sewer (RCP) |
L.F. |
249 |
$
34.00 |
$ 8,466.00 |
$
54.00 |
$ 13,446.00 |
$
38.00 |
$ 9,462.00 |
18 |
12"
End Section (RC) |
Each |
1 |
$
400.00 |
$ 400.00 |
$
432.00 |
$ 432.00 |
$
400.00 |
$ 400.00 |
19 |
Flowable
Fill for Storm Sewer |
L.F. |
195 |
$
15.00 |
$ 2,925.00 |
$
43.20 |
$ 8,424.00 |
$
25.00 |
$ 4,875.00 |
20 |
Keystone
Compaq Retaining Wall |
L.F. |
126 |
$
52.20 |
$ 6,577.20 |
$
52.35 |
$ 6,596.10 |
$
60.00 |
$ 7,560.00 |
21 |
3"
PVC Conduit for Water Service |
L.F. |
88.0 |
$
11.00 |
$ 968.00 |
$
50.00 |
$ 4,400.00 |
$
20.00 |
$ 1,760.00 |
22 |
Permanent
Signing |
L.S. |
1 |
$
4,750.00 |
$ 4,750.00 |
$
4,762.80 |
$ 4,762.80 |
$
4,850.00 |
$ 4,850.00 |
23 |
Pavement
Markings |
L.S. |
1 |
$
5,600.00 |
$ 5,600.00 |
$
5,612.23 |
$ 5,612.23 |
$
5,725.00 |
$ 5,725.00 |
24 |
Silt Fence |
L.F. |
416 |
$
1.50 |
$ 624.00 |
$ 2.75 |
$ 1,144.00 |
$ 2.00 |
$ 832.00 |
25 |
Temporary Curb Inlet Sediment Barrier |
Each |
2 |
$
100.00 |
$ 200.00 |
$
109.01 |
$ 218.02 |
$
150.00 |
$ 300.00 |
26 |
Temporary
Seeding |
L.S. |
1 |
$
880.00 |
$ 880.00 |
$
2,700.00 |
$ 2,700.00 |
$
1,500.00 |
$ 1,500.00 |
27 |
Lighting |
L.S. |
1 |
$
32,125.00 |
$ 32,125.00 |
$
32,238.00 |
$ 32,238.00 |
$
35,000.00 |
$ 35,000.00 |
28 |
Traffic
Control |
L.S. |
1 |
$
8,700.00 |
$ 8,700.00 |
$
8,731.80 |
$ 8,731.80 |
$
9,000.00 |
$ 9,000.00 |
29 |
Construction
Staking |
L.S. |
1 |
$
4,590.00 |
$ 4,590.00 |
$
6,037.20 |
$ 6,037.20 |
$
8,600.00 |
$ 8,600.00 |
30 |
Seeding,
Fertilizing and Mulching |
L.S. |
1 |
$
1,450.00 |
$ 1,450.00 |
$
2,700.00 |
$ 2,700.00 |
$
3,000.00 |
$ 3,000.00 |
31 |
Mobilization |
L.S. |
1 |
$
8,040.00 |
$ 8,040.00 |
$
17,100.01 |
$ 17,100.01 |
$
20,000.00 |
$ 20,000.00 |
|
TOTAL SECTION 2 |
|
|
|
$ 421,667.40 |
|
$ 498,065.52 |
|
$ 488,677.60 |
|
LAKE VIEW ADDITION STORM
SEWER - SECTION 3 |
|
|
|
|
|
1 |
Clearing
and Grubbing |
L.S. |
1 |
$
1,100.00 |
$ 1,100.00 |
$
2,580.00 |
$ 2,580.00 |
8000 |
$ 8,000.00 |
2 |
36"
CMP |
L.F. |
374 |
$
94.00 |
$ 35,156.00 |
$
93.96 |
$
35,141.04 |
91 |
$ 34,034.00 |
3 |
42" CMP |
L.F. |
175 |
$
102.00 |
$ 17,850.00 |
$
102.60 |
$ 17,955.00 |
115 |
$ 20,125.00 |
4 |
48" CMP |
L.F. |
55 |
$
107.00 |
$ 5,885.00 |
$
106.92 |
$ 5,880.60 |
127 |
$ 6,985.00 |
5 |
48" Metal End
Section |
Each |
1 |
$
1,290.00 |
$ 1,290.00 |
$
1,296.00 |
$ 1,296.00 |
1000 |
$ 1,000.00 |
6 |
6'
x 4' Curb Inlet |
Each |
1 |
$
3,330.00 |
$ 3,330.00 |
$
3,348.00 |
$ 3,348.00 |
2800 |
$ 2,800.00 |
7 |
6'
x 6' Curb Inlet |
Each |
1 |
$
3,330.00 |
$ 3,330.00 |
$
3,348.00 |
$ 3,348.00 |
3600 |
$ 3,600.00 |
8 |
6'
x 4' Junction Box |
Each |
1 |
$
3,010.00 |
$ 3,010.00 |
$
3,024.00 |
$ 3,024.00 |
6600 |
$ 6,600.00 |
9 |
6' x 6' Junction Box |
Each |
1 |
$
3,440.00 |
$ 3,440.00 |
$
3,456.00 |
$ 3,456.00 |
5200 |
$ 5,200.00 |
10 |
5' x 5' Junction Box |
Each |
2 |
$
3,010.00 |
$ 6,020.00 |
$
3,024.00 |
$ 6,048.00 |
3500 |
$ 7,000.00 |
11 |
18"
Nominal Diameter Rip-Rap |
S.Y. |
44 |
$
32.00 |
$ 1,408.00 |
$
58.32 |
$ 2,566.08 |
60 |
$ 2,640.00 |
12 |
Unclassified
Excavation |
C.Y. |
4389 |
$
1.00 |
$ 4,389.00 |
$ 1.15 |
$ 5,047.35 |
15 |
$ 65,835.00 |
13 |
Compaction
of Earthwork |
C.Y. |
1713 |
$
0.50 |
$ 856.50 |
$ 1.15 |
$ 1,969.95 |
2 |
$ 3,426.00 |
14 |
Seeding,
Fertilizing and Mulching |
L.S. |
1 |
$
2,830.00 |
$ 2,830.00 |
$
3,780.00 |
$ 3,780.00 |
5000 |
$ 5,000.00 |
|
TOTAL SECTION 3 |
|
|
|
$ 89,894.50 |
|
$ 95,440.02 |
|
$ 172,245.00 |
|
|
|
|
|
|
|
|
|
|
|
GRAND
TOTAL OF SECTIONS 1, 2 AND 3 |
|
|
|
$ 817,740.00 |
|
$ 957,130.12 |
|
$
1,082,285.31 |
|
|
|
|
|
|
|
|
|
|
|
|