CLINTON PARKWAY AND WAKARUSA RELIEF SEWER (PROJ.#PS04-33)
FINAL REPORT
This report provides information regarding the recently completed Capital Improvement Project #PS04-33, also known as the Clinton Parkway & Wakarusa Drive Relief Sewer. A map of the project area is shown below.
General Project Information
The goal
of the project was to install a relief sewer that would enable the City to
decommission Pump Station # 33, located at 4820 Clinton Parkway. PS 33, installed in 1994 to serve development north of
Clinton Parkway and east of Wakarusa, was located next to a drainage way at the
bottom of a hill (see photo #1). This location made accessibility for
maintenance difficult. Decommissioning of this station would result in
substantial savings in maintenance costs and utility (phone, electric) costs.
Photo #1
The relief sewer would convey flows by gravity from the pump station wet well to a sewer system on the south side of Clinton Parkway.
Table 1 presents information related to the schedule of the project.
Engineering Proposals Received |
04/24/04 |
Bids Opened |
10/26/04 |
Working Days Allotted |
40 |
Working Days Used |
38 |
Notice to Proceed Given |
1/31/05 |
Final Completion Date |
3/25/05 |
Table 1
Professional Engineering Consultants, P.A. (PEC) was selected as the consultant for the project. Nowak Construction Company was the low bidder on the project and was awarded the construction contract.
Graph 1 provides information on the engineering and construction costs of the project.
Graph 2 provides a breakdown of engineering costs.
|
|
Graph 1 Graph 2
Table 2 presents information regarding cost of the project
Engineer’s Estimate of Construction Cost |
$108,865 |
Construction Costs |
$79,185 |
Easement Costs |
$26,720 |
Engineering Costs |
$34,888 |
Change Orders |
0 |
Change Order Amounts (+/-) |
$00.00 |
Total Cost of Project |
$140,793 |
2003 Master Plan Projected Cost |
$260,000 |
Table 2
Project Photographs
|
|
Fusing the HDPE pipe segments together HDPE pipe train in field (555’)
|
|
HDPE pipe being pulled by existing lift stations Drilling rig pulling pipe under Clinton Parkway