City of Lawrence |
|
|
|
|
|
|
|
|
Project
01-SR1-105(S) |
|
6th
Street, Missouri Street to Massachusetts Street |
|
Milling,
Overlay, Pavement Marking (KLINK) |
|
BID
TAB |
|
Engineer's
Estimate: $482,926.30 |
|
Bid Date: April 26, 2005 |
|
|
LRM
Industries, Inc. |
R. D. Johnson Excavating, Co. |
|
Item |
Description |
Quantity |
Unit |
Unit Price |
Amount |
Unit Price |
Amount |
|
1 |
Milling 2" Depth
(P) |
27,654 |
S.Y. |
$
1.35 |
$ 37,332.90 |
$
1.50 |
$ 41,481.00 |
|
2 |
Milling 2" Depth
(NP) |
1,005 |
S.Y. |
$
1.35 |
$ 1,356.75 |
$
1.50 |
$ 1,507.50 |
|
3 |
Asphaltic Concrete
(BM-2, Special) 2" Overlay (P)* |
3,195 |
TON |
$
36.30 |
$
115,978.50 |
$
38.00 |
$ 121,410.00 |
|
4 |
Asphaltic Concrete
(BM-2, Special) 2" Overlay (NP)* |
140 |
TON |
$
54.00 |
$ 7,560.00 |
$
38.00 |
$ 5,320.00 |
|
5 |
Concrete Pavement
Patch (Full Depth) (P)*** |
250 |
S.Y. |
$
110.00 |
$ 27,500.00 |
$
110.00 |
$ 27,500.00 |
|
6 |
Asphalt Pavement
Patch (Full Depth) (P)*** |
100 |
TON |
$
105.00 |
$ 10,500.00 |
$
100.00 |
$ 10,000.00 |
|
7 |
Crackfilling (P)*** |
100 |
L.F. |
$
2.00 |
$ 200.00 |
$
3.00 |
$ 300.00 |
|
8 |
Demolition (See Sheet
13 and General Notes) (P) |
1 |
L.S. |
$
6,400.00 |
$ 6,400.00 |
$
39,800.00 |
$ 39,800.00 |
|
9 |
10" High Early
Durable Portland Cement Concrete (P) |
692 |
S.Y. |
$
80.00 |
$ 55,360.00 |
$
87.00 |
$ 60,204.00 |
|
10 |
Modified 24"
Concrete Curb and Gutter (P) |
260 |
L.F. |
$
23.25 |
$ 6,045.00 |
$
34.50 |
$ 8,970.00 |
|
11 |
Remove & Replace
Modified 30" Curb & Gutter (NP) |
520 |
L.F. |
$
29.50 |
$ 15,340.00 |
$
39.00 |
$ 20,280.00 |
|
12 |
Remove & Replace
24" Curb & Gutter (NP) |
2,045 |
L.F. |
$
21.00 |
$ 42,945.00 |
$
28.00 |
$ 57,260.00 |
|
13 |
4" Concrete
Sidewalk (See Spec Book for Standard Details) (NP) |
20 |
S.Y. |
$
55.00 |
$ 1,100.00 |
$
30.80 |
$ 616.00 |
|
14 |
6' Concrete Access
Ramp (NP) |
15 |
EACH |
$
1,180.00 |
$ 17,700.00 |
$
1,150.00 |
$ 17,250.00 |
|
15 |
Standard 8' x 4'
Storm Sewer Curb Inlet (NP) |
2 |
EACH |
$
3,800.00 |
$ 7,600.00 |
$
4,000.00 |
$ 8,000.00 |
|
16 |
Standard 6' x 4'
Storm Sewer Curb Inlet (NP) |
1 |
EACH |
$
3,300.00 |
$ 3,300.00 |
$
3,600.00 |
$ 3,600.00 |
|
17 |
Standard 5' X 4'
Storm Sewer Curb Inlet (NP) |
2 |
EACH |
$
3,100.00 |
$ 6,200.00 |
$
3,400.00 |
$ 6,800.00 |
|
18 |
Seed, Fertilize and
Mulch (NP) |
1 |
L.S. |
$
2,600.00 |
$ 2,600.00 |
$
4,000.00 |
$ 4,000.00 |
|
19 |
Traffic Control (P) |
1 |
L.S. |
$
15,165.00 |
$ 15,165.00 |
$
10,000.00 |
$ 10,000.00 |
|
20 |
6" Broken White
Lane Line (Class A) (P) (Applied to Asphalt) |
1,400 |
L.F. |
$
3.05 |
$ 4,270.00 |
$
3.30 |
$ 4,620.00 |
|
21 |
6" Broken White
Lane Line (Class A) (P) (Applied to Concrete)**** |
70 |
L.F. |
$
2.10 |
$ 147.00 |
$
2.30 |
$ 161.00 |
|
22 |
6" Dotted White
Lane Line (Class A) (P) |
122 |
L.F. |
$
3.05 |
$ 372.10 |
$
3.30 |
$ 402.60 |
|
23 |
6" Dotted White
Extension Line (Class A) (P) |
154 |
L.F. |
$
3.05 |
$ 469.70 |
$
3.30 |
$ 508.20 |
|
24 |
6" Solid White
Channelization Line (Class A) (P) |
2,379 |
L.F. |
$
3.05 |
$ 7,255.95 |
$
3.30 |
$ 7,850.70 |
|
25 |
6" Solid White
Edge Line (Class A) (P) |
94 |
L.F. |
$
3.00 |
$ 282.00 |
$
3.30 |
$ 310.20 |
|
26 |
12" Solid White
Diagonal Line (Class A) (P) |
172 |
L.F. |
$
5.00 |
$ 860.00 |
$
6.70 |
$ 1,152.40 |
|
27 |
24" Solid White
Stop Line (Class A) (P) (Applied to Asphalt) |
427 |
L.F. |
$
7.40 |
$ 3,159.80 |
$
7.80 |
$ 3,330.60 |
|
28 |
24" Solid White
Stop Line (Class A) (P) (Applied to Concrete)**** |
27 |
L.F. |
$
10.20 |
$ 275.40 |
$
11.00 |
$ 297.00 |
|
29 |
36" Solid White
Crosswalk Line (Class A) (P) |
444 |
L.F. |
$
11.00 |
$ 4,884.00 |
$
11.50 |
$ 5,106.00 |
|
30 |
4" Broken Yellow
Lane Line (Class B) (P) |
960 |
L.F. |
$
2.05 |
$ 1,968.00 |
$
2.20 |
$ 2,112.00 |
|
31 |
4" Solid Yellow
Lane Line (Class B) (P) (Applied to Asphalt) |
3,894 |
L.F. |
$
2.05 |
$ 7,982.70 |
$
2.20 |
$ 8,566.80 |
|
32 |
4" Solid Yellow
Lane Line (Class B) (P) (Applied to Concrete) |
259 |
L.F. |
$
2.05 |
$ 530.95 |
$
2.20 |
$ 569.80 |
|
33 |
4" Solid Double
Yellow Lane Line (Class B) (P)** |
671 |
L.F. |
$
4.10 |
$ 2,751.10 |
$
4.40 |
$ 2,952.40 |
|
34 |
12" Solid Yellow
Diagonal Line (Class B) (P) |
153 |
L.F. |
$
6.30 |
$ 963.90 |
$
6.70 |
$ 1,025.10 |
|
35 |
Left Turn Lane -- Use
Arrow (P) |
31 |
EACH |
$
170.00 |
$ 5,270.00 |
$
165.00 |
$ 5,115.00 |
|
36 |
Right Turn Lane --
Use Arrow (P) |
2 |
EACH |
$
170.00 |
$ 340.00 |
$
165.00 |
$ 330.00 |
|
37 |
Through Lane -- Use
Arrow (P) (Applied to Asphalt) |
4 |
EACH |
$
185.00 |
$ 740.00 |
$
200.00 |
$ 800.00 |
|
38 |
Through Lane -- Use
Arrow (P) (Applied to Concrete)**** |
2 |
EACH |
$
185.00 |
$ 370.00 |
$
200.00 |
$ 400.00 |
|
39 |
Sanitary Sewer
Manhole Adjustment (NP)***** |
1 |
EACH |
$
700.00 |
$ 700.00 |
$
750.00 |
$ 750.00 |
|
40 |
Storm Sewer Manhole
Adjustment (NP)***** |
2 |
EACH |
$
700.00 |
$ 1,400.00 |
$
750.00 |
$ 1,500.00 |
|
41 |
Water Valve Box
Adjustment (NP)***** |
12 |
EACH |
$
185.00 |
$ 2,220.00 |
$
250.00 |
$ 3,000.00 |
|
42 |
Water Meter Box
Adjustment (NP)***** |
1 |
EACH |
$
185.00 |
$ 185.00 |
$
300.00 |
$ 300.00 |
|
43 |
Loop Detector
Installation (P)***** |
608 |
L.F. |
$
9.70 |
$ 5,897.60 |
$
12.00 |
$ 7,296.00 |
|
|
GRAND TOTAL |
|
|
|
$ 433,478.35 |
|
$ 502,754.30 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|