Set Bid Date for Waterline Relocation at Kasold Bridge and KS Turnpike:

 

Project History The current project includes waterline relocation work that is necessary due to future street and drainage improvements ( Public Works project) along Kasold and the bridge over the Kansas Turnpike. The project  requires relocation of approximately 400  ft of  12 inch waterline. 

 

Project Status / Details:   The design for the street and waterline relocation work was completed by PEC engineers.  Notification was provided by Public Works that the waterline required adjustment prior to beginning street / drainage construction.  The anticipated  schedule for the work at this time:

 

Bid Letting – July 26th

Notice to Proceed  - August 16th

End Construction – End of September   

 

Project Funding: 

Funding for this project will come from the non-bonded construction fund for 2005 waterline improvements.  This fund provides approximately $1,000,000 per year for waterline and treatment plant improvements .

Action Request.  The Utilities Department is seeking approval from the City Commission to set a bid date of July 26th for the Waterline Relocation at Kasold Bridge and the Kansas Turnpike.

 