Completed Tasks through October 21, 2005 |
Anticipated Tasks for November 2005 |
Completed all background work. This includes development of project procedures manual, updated schedule, and completed B&V project website.
Developed preliminary list for PAC and Peer groups. List was updated at project initiation meeting.
Confirmed selection of PAC and Peer groups. Mayor has sent invitations to PAC asking to be part of process.
Began development of Public Involvement Program. Public involvement will include media, kiosks, and public website. A public website with links to City website is being developed.
Scheduled first PAC and Public meeting. Meetings to be held October 26th and November 23rd, respectively.
|
Complete Stakeholder interviews. Interviews will be documented in a report.
Complete first PAC and Public Meeting. Meetings will be documented and meeting minutes will be placed on Public Website.
Begin preliminary process evaluations for four options.
Complete Peer Group interviews.
Conduct workshop No. 1 on Nov 15th. Time to be determined.
Schedule meetings with Haskell University and City/County Commissioners meeting to review project goals.
Project website to be up and running prior to Nov 3rd meeting. Will be linked from City’s website. |
Actions/Issues Population growth may accelerate need for Wakarusa WRF prior to 2011. Important to maintain project timeline.
Actual-to-date engineering costs exceed forecasts due to project initiation activities. |
|
Decisions Needed None at this time. |