2006 PROJECT FILES  
City Projects
      P.O. Plans Commission Eng Fee Est Inspection
Fees
Completion
Project Number Project Name Contractor Amount Approved Approval 5% 3%  
8-SR2-206(C) 2006 Crack Seal Program, Phase 1 Vance Bros.  $      452,500.00 3-Feb-06 7-Feb-06  $      22,625.00  $        13,575.00 15-Nov-06
9-SR3-206(C) 2006 Overlay Program, Phase 1 LRM  $      947,630.00 27-Feb-06 28-Feb-06  $      47,381.50  $        28,428.90 3-Aug-06
11-SR4-306(C) 2006 Overlay Program, Phase 2 RD Johnson  $   1,365,098.18 27-Mar-06 28-Mar-06  $      68,254.91  $        40,952.95 4-Aug-06
12-SR5-306(C) 2006 Overlay Program, Phase 3 Kansas Heavy  $   1,232,288.54 8-May-06 9-May-06  $      61,614.43  $        36,968.66 14-Sep-06
18-CP5-506(C) Alley Reconstruction 10th Street to 11th Street between Massachusetts Street & New Hampshire Street  $      10,000.00  $          3,000.00
22-CP7-606(C) New Hampshire Street, Street Improvements (Mill, Overlay, Pavement Marking, Intersection Reconstruction, Mid-Block Ped Crossings) between 6th Street and 9th Street RD Johnson  $      273,097.15 14-Aug-06 15-Aug-06  $      16,385.83  $          8,192.91 21-Oct-06
28-AI1-906(C) 2006 Airport Improvements Hamm, Inc.  -  - - -  $        11,893.39 30-Oct-06  
Total Engineering/Inspection Fees  $     226,261.67  $      143,011.81
State Projects
Project Number Project Name Contractor P.O.Amount Start Date   Engineering Inspection Completion
Date
 
01-SR1-106(S)
State/City  50/50
Iowa, Irving Hill Road Overpass to Harvard; 23rd St.;  State Project No. 53/10-23 U-2043-01 LRM Industries $534,942.25 26-Jun-06    $      20,000.00  $          5,523.44 28-Jul-06
Private Projects
        Authori- Acceptance   Inspection  
      Amount zation to Letter Inspection Fee Completion
Project Number Project Name Contractor Escrowed Proceed Mailed Fee Rec'd Amount Date
02-SS1-106(P) Stoneridge East    
03-CP1-106(P) Stoneridge East            
04-SS2-106(P) Langston Heights  
05-CP2-106(P) Langston Heights            
06-SS3-106(P) Lake Pointe PCD  
07-SW1-106(P) 500 Locust St, Sidewalk & Curb Reconst. Jim Hicks   Work started w/o atp        
10-SS4-306(P) Park West Additional Sanitary Sewer McLouth Excav. na 1-May-06 19-May-06 14-Jun-06 $302.58 12-May-06  
13-SS5-306(P) Lot 3, Block 2, Lake View Addition No. 2 McLouth Excav. $91,312.00 1-Jun-06 21-Jun-06 10-Jul-06 $3,769.80 20-Jun-06  
14-ST1-406(P) Lot 3, Block 2, Lake View Addition No. 2 McLouth Excav. $145,769.00 15-Jun-06 12-Jul-06 18-Jul-06 $440.40 26-Jun-06  
16-SS6-506(P) Mary's Lake Addition RD Johnson $720,000.00 23-Oct-06  
17-CP4-506(P) Mary's Lake Addition RD Johnson $720,000.00 9-Oct-06        
20-SS7-506(P) North Lawrence Addition No. 8 RD Johnson $13,924.00 21-Jul-06 28-Jul-06 $398.22 24-Jul-06  
21-SS8-606(P) MP Builders Addition (N.9th and Elm) McLouth Exc $24,914.00 28-Jul-06 8-Aug-06   $747.42 3-Aug-06  
23-ST2-606(P) Tennesse Street and Gower Place (Sigma Chi)  
24-SS9-606(P) Homewood Gardens Addition, Replat            
29-SS12-906(P) Glenwood Addition  
30-ST3-906(P) Glenwood Addition            
3-CP1-102(BD) Monterey South, Stetson to Peterson King Const $1,136,020.00   $34,080.60  
32-CP6-603(BD) Monterey North, Peterson Rd to Grand Vista King Const $1,132,166.00 $33,964.98
33-CP7-603(BD) Peterson Rd, Kasold to Monterey Way King Const $2,020,078.00   $60,602.34  
Total Inspection Fees $134,306.34
2006 Engineering    $246,261.67
2006 Inspection   $282,841.59