2005 PROJECT
FILES |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
City Projects |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Contract |
Work |
|
Engineering |
|
|
|
|
|
|
|
|
P.O. |
Documents |
Order |
Completion |
Fee |
Inspection |
|
|
Project Number |
Project Name |
Amount |
Contractor |
P.O. No. |
Amount |
Signed |
Start Date |
Date |
Estimate |
Fee |
|
|
09-SR2-205(C) |
2005 Overlay Program, Phase 1 |
$700,000.00 |
LRM Industries |
62373 |
$739,903.58 |
|
13-Jun-05 |
|
$36,995.18 |
$22,197.11 |
|
|
12-CR1-205(C) |
2005 Concrete Repair
Program |
$700,000.00 |
Pavers, Inc. |
62575 |
$384,989.00 |
|
25-Jul-05 |
|
$19,249.45 |
$11,549.67 |
|
|
16-SR3-305(C) |
2005 Chip and Seal
Program |
na |
Vance Bros. |
62421 |
$157,372.70 |
|
|
|
$7,868.64 |
$4,721.18 |
|
|
20-SR4-405(C) |
2005 Overlay Program,
Phase 2 |
$700,000.00 |
LRM Industries |
|
$767,065.55 |
|
11-Jul-05 |
|
$38,353.28 |
$23,011.97 |
|
|
21-SR5-405(C) |
2005
Overlay and Concrete, Phase 3 |
na |
Kansas Heavy |
62450 |
$708,355.33[1] |
30-Jun-05 |
18-Jul-05 |
|
$35,417.77 |
$21,250.66 |
|
|
33-PW1-605(C) |
Wakarusa Service
Center, Master Plan |
|
|
|
|
|
|
|
$0.00 |
$0.00 |
|
|
51-SI1-1005(C) |
2005 Traffic Signal
Renovations |
$300,000.00 |
|
|
|
|
|
|
$0.00 |
$0.00 |
|
|
54-SW3-1105(C) |
Yale
Road, West of Iowa Street, Sidewalk |
na |
Morgan Concr. |
63716 |
$28,624.00 |
|
30-Jan-06 |
|
|
|
|
|
58-BR1-1105(C) |
HVAC Reconstruction,
2nd Floor, City Hall |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Benefit
District Projects |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Request |
|
|
|
|
|
Work |
Engineering |
|
|
|
|
for |
|
|
|
|
P.O. |
Order |
Fee |
Inspection |
|
Project Number |
Project Name |
Improve. |
Amount |
Consultant |
Contractor |
P.O. No. |
Amount |
Start Date |
Estimate |
Fee |
|
15-CP4-305(BD) |
Hanscom-Tappan Subdivision |
public hearing 7-19-05 |
$
350,000.00 |
Landplan |
RD Johnson |
63145 |
$130,099.25 |
14-Nov-05 |
|
$3,902.98 |
|
22-GI2-405(BD) |
33rd and Nieder Road, Geometric Improvements |
|
|
|
|
|
|
|
|
|
|
45-GI5-905(BD) |
K-10 and O'Connell
Road, Left Turn Lane, Geometric Improvements |
|
|
Peridian |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Private
Projects |
|
|
|
|
|
|
|
|
|
|
Plans |
Plans |
|
|
Inspection |
|
|
Engineering |
|
|
|
|
|
Approved |
Approved |
|
Amount |
Fee |
Inspection |
Completion |
Fee |
Inspection |
|
|
Project Number |
Project Name |
City Eng. |
Dir. Utilities |
Contractor |
Escrowed |
Amount |
Fee Rec'd |
Date |
Estimate |
Fee |
|
|
02-SS1-105(P) |
Lot 2, Oread
West No. 14 (Family Health) |
17-Feb-05 |
16-Feb-05 |
RD Johnson |
$9,542.00 |
|
|
|
|
|
|
|
03-ST1-105(P) |
Lot
2, Oread West No. 14 (Family Health) |
20-Jun-05 |
na |
|
|
|
|
|
|
|
|
|
04-CP1-105(P) |
N 7th and Elm |
14-Mar-05 |
31-Jan-05 |
|
|
|
|
|
|
|
|
|
06-SS2-105(P) |
Stoneridge North
Subdivision |
3-May-05 |
18-Apr-05 |
McLouth Exc. |
$271,898.00 |
$5,922.09 |
27-Jul-05 |
12-Jul-05 |
|
$5,922.09 |
|
|
07-CP2-105(P) |
Stoneridge North
Subdivision |
28-Jun-05 |
13-Jun-05 |
McLouth Exc. |
$1,044,364.95 |
$24,143.12 |
15-Dec-05 |
6-Dec-05 |
|
$24,143.12 |
|
|
08-SS3-205(P) |
Carpenter Addition
No. 2 |
22-Apr-05 |
16-Feb-05 |
J&H Constr. |
none |
$390.30 |
6-Oct-05 |
26-May-05 |
|
$390.30 |
|
|
10-SS4-205(P) |
Salvation Army |
20-Jun-05 |
16-Feb-05 |
LRM Indust. |
$140,000.00 |
|
|
|
|
|
|
|
11-ST2-205(P) |
Carpenter Addition
No. 2 |
|
|
|
|
|
|
|
|
|
|
|
13-SS5-205(P) |
Hanscom-Tappan
Subdivision |
19-Apr-05 |
18-Apr-05 |
Linaweaver |
$75,998.90 |
$2,273.07 |
|
15-Nov-05 |
|
$2,273.07 |
|
|
14-CP3-205(P) |
Hanscom-Tappan
Subdivision |
25-May-05 |
|
Linaweaver |
$280,286.15 |
$7,157.74 |
6-Sep-06 |
31-Dec-05 |
|
$7,157.74 |
|
|
17-SS6-405(P) |
Ironwood
North Additional sanitary sewer |
20-Apr-05 |
na |
McLouth Exc. |
$20,000.00 |
$495.39 |
13-Jun-05 |
18-May-05 |
|
$495.39 |
|
|
18-SS7-405(P) |
Oregon
Trail Addition, Sanitary Sewer Improvements |
|
18-Apr-05 |
|
|
|
|
|
|
|
|
|
19-CP5-405(P) |
Oregon
Trail Addition, Street, Storm Sewer, Waterline Improvements |
|
|
|
|
|
|
|
|
|
|
|
23-SS8-405(P) |
Fox
Chase South No. 3, Sanitary Sewer Improvements (Lines J,K,L,M) |
19-Jan-06 |
na |
King's Constr. |
$95,889.40 |
$2,804.68 |
21-Aug-06 |
31-Jul-06 |
|
$2,804.68 |
|
|
24-CP6-405(P) |
Fox
Chase South No. 3, Street, Storm Sewer, Waterline Improvements |
19-Jan-06 |
23-Jan-06 |
|
|
|
|
|
|
|
|
|
25-SS9-505(P) |
Doolittle
Subdivision, Sanitary Sewer Improvements |
6-Jan-06 |
na |
|
|
|
|
|
|
|
|
|
26-CP7-505(P) |
Doolittle
Subdivision, Street, Storm Sewer, Waterline Improvements |
20-Dec-05 |
15-Dec-05 |
|
|
|
|
|
|
|
|
|
28-SS10-505(P) |
Family
Video (19th and Mass), Sanitary Sewer Improvements |
14-Sep-05 |
na |
Rockford |
$15,500.00 |
$465.00 |
26-Jan-06 |
28-Nov-05 |
|
$465.00 |
|
|
29-SS11-605(P) |
Hutton
Farms West No. 1, Sanitary Sewer Improvements |
1-Aug-05 |
26-Jul-05 |
Emery Sapp |
-- |
$8,113.80 |
21-Jun-06 |
8-Mar-06 |
|
$8,113.80 |
|
|
30-CP8-605(P) |
Hutton
Farms West No. 1, Street, Storm Sewer, Waterline Improvements |
2-Sep-05 |
1-Sep-05 |
Emery Sapp |
-- |
$11,156.51 |
5-Jun-06 |
22-May-06 |
|
$11,156.51 |
|
|
31-GI4-605(P) |
1800
Blk of Massachusetts & New Hampshire (Family Video), Geometric Impr. |
14-Sep-05 |
na |
Rockford |
$13,134.00 |
$394.02 |
26-Jan-06 |
23-Jan-06 |
|
$394.02 |
|
|
32-SS12-605(P) |
Lake
Estates at Alvamar |
28-Oct-05 |
28-Oct-05 |
Redford Con |
$189,027.00 |
$5,670.81 |
14-Jul-06 |
1-Mar-06 |
|
$5,670.81 |
|
|
34-SW1-605(P) |
202 N. 5th
Street, Sidewalk, Storm Sewer Improvements |
29-Sep-05 |
26-Sep-05 |
Lawrenz |
|
|
|
|
|
|
|
|
35-ST3-605(P) |
4101
W. 6th Street (Lot 1, Free State Veterinary Hospital), Storm Sewer Impr. |
23-Aug-05 |
na |
|
|
|
|
|
|
|
|
|
36-CP9-705(P) |
Lake
Estates at Alvamar, Street, Storm Sewer, Waterline Improvements |
28-Oct-05 |
28-Oct-05 |
RD Johnson |
$550,432.00 |
$14,257.80 |
14-Jul-06 |
30-Jun-06 |
SWPPP issues. |
$14,257.80 |
|
|
37-CP10-705(P) |
8th
and New Hampshire (Southeast Corner), Street, Parking Impr. |
25-Oct-05 |
na |
RD Johnson |
$35,317.67 |
$1,028.68 |
10-Oct-06 |
12-Jan-06 |
|
$1,028.68 |
|
|
38-SS13-805(P) |
Homewood
Gardens Suburban Addition, Sanitary Sewer Improvements |
15-Aug-05 |
na |
Conley |
$11,000.00 |
$330.00 |
15-Dec-06 |
17-Oct-05 |
|
$330.00 |
|
|
39-SS14-805(P) |
Habitat
Neighborhood Addition No. 5, Sanitary Sewer Improvements |
20-Jan-06 |
na |
Kings Cons. |
na |
$2,102.08 |
13-Jul-06 |
29-Jun-06 |
|
$2,102.08 |
|
|
40-CP11-805(P) |
Habitat
Neighborhood Addition No. 5, Street, Storm Sewer, Waterline Improvements |
20-Jan-06 |
23-Jan-06 |
Kings Cons. |
na |
$5,690.28 |
18-Jan-07 |
25-Jul-06 |
|
$5,690.28 |
|
|
41-SS15-805(P) |
The
Cove, Sanitary Sewer Improvements |
27-Dec-05 |
na |
McLouth Excavating |
$114,497.50 |
$3,784.89 |
30-May-06 |
16-May-06 |
|
$3,784.89 |
|
|
42-CP12-805(P) |
The
Cove, Street, Storm Sewer, Waterline Improvements |
19-Jan-06 |
23-Jan-06 |
Kings Co, McLouth Excavating |
$335,485.15 |
$7,810.76 |
14-Jul-06 |
14-Jun-06 |
|
$7,810.76 |
|
|
43-SW2-905(P) |
700
E. 22nd Street, Sidewalk Improvements and Driveway Closures on Haskell Avenue |
13-Oct-05 |
na |
Joel Fritzel |
$8,349.60 |
$250.49 |
2-Mar-06 |
1-Mar-06 |
|
$250.49 |
|
|
44-CR2-905(P) |
1309
W. 6th Street (McDonald's), Curb and Gutter Improvements |
6-Oct-05 |
na |
|
|
|
|
|
|
|
|
|
46-SS16-905(P) |
Hutton
Farms West No. 2, Sanitary Sewer Improvements |
24-Jan-06 |
na |
|
|
|
|
|
|
|
|
|
47-ST4-905(P) |
Hutton
Farms West No. 2, Storm Sewer and Waterline Improvements |
|
|
|
|
|
|
|
|
|
|
|
48-SS17-1005(P) |
Sherylville
Estates, Sanitary Sewer Improvements |
27-Dec-05 |
22-Dec-05 |
Kings Cons. |
$31,530.00 |
$994.82 |
Utilities |
12-Sep-06 |
|
$994.82 |
|
|
49-CP13-1005(P) |
Sherylville
Estates, Storm Sewer and Waterline Improvements |
4-Jan-06 |
3-Jan-06 |
Kings Cons. |
$207,042.67 |
$4,806.05 |
5-Nov-06 |
27-Nov-06 |
|
$4,806.05 |
|
|
50-SS18-1005(P) |
Sherylville
Estates, Pump Station No. 35
Improvements |
na |
25-Aug-06 |
Kings Cons. |
$26,529.60 |
$1,482.44 |
Utilities |
28-Nov-06 |
|
$1,482.44 |
|
|
|
52-SS19-1005(P) |
Fall
Creek Farms, 12th Plat, Sanitary Sewer Improvements |
12-Dec-05 |
9-Dec-05 |
Kings Cons. |
$24,493.05 |
$734.79 |
Utilities |
28-Sep-06 |
|
$734.79 |
|
|
|
53-CP14-1005(P) |
Fall
Creek Farms, 12th Plat, Street, Storm Sewer, Waterline Improvements |
3-Jan-06 |
29-Dec-05 |
Kings Cons. |
$275,359.75 |
$7,460.61 |
26-Dec-06 |
30-Nov-06 |
|
$7,460.61 |
|
|
|
55-SS20-1105(P) |
Lot
1, Crossgates No. 3, Sanitary Sewer Extension |
12-Dec-05 |
na |
McLouth Excavating |
$31,682.00 |
$932.76 |
|
25-Jan-06 |
|
$932.76 |
|
|
|
56-GI6-1105(P) |
31st
and Lawrence Avenue, Turn Lane Improvements |
28-Jan-06 |
na |
RD Johnson |
$60,000.00 |
$1,747.88 |
|
1-Dec-06 |
|
$1,747.88 |
|
|
|
57-SS21-1105(P) |
Green
Tree Subdivision No. 2, Sanitary Sewer Improvements |
23-Dec-05 |
na |
McLouth Exc. |
|
-- |
-- |
17-Jan-06 |
|
-- |
|
|
|
59-SW4-1105(P) |
201-209
W. 8th Street, Sidewalk and Curb Reconstruction |
17-May-06 |
na |
Gene Fritzel Construction Co., Inc. |
$62,025.00 |
|
|
|
|
|
|
|
|
60-SS22-1105(P) |
Park
West Gardens, Sanitary Sewer Improvements |
10-Jan-06 |
na |
McLouth Exc. |
$34,232.50 |
$1,026.98 |
25-May-06 |
12-May-06 |
|
$1,026.98 |
|
|
|
|
|
|
State Projects |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Engineering |
|
|
|
|
State-City |
|
City Share |
P.O. |
Start Date |
Completion |
|
Fee |
Inspection |
|
Project Number |
Project Name |
Shares |
Contractor |
P.O. No. |
Amount |
|
Date |
|
Estimate |
Fee |
|
01-SR1-105(S) |
6th Street, Arkansas to Mass. |
50/50 |
LRM Industries |
62364 |
$433,478.35 |
6-Jun-05 |
10-Aug-05 |
|
$
16,000.00 |
$
4,334.78 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Total Engineering/Inspection
Fees |
$153,884.31 |
$214,396.18 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|