2005 PROJECT FILES  
City Projects
            Contract Work   Engineering  
          P.O. Documents Order Completion Fee Inspection
Project Number Project Name Amount Contractor P.O. No. Amount Signed Start Date Date Estimate Fee
09-SR2-205(C) 2005 Overlay Program, Phase 1 $700,000.00 LRM Industries 62373 $739,903.58   13-Jun-05   $36,995.18 $22,197.11
12-CR1-205(C) 2005 Concrete Repair Program $700,000.00 Pavers, Inc. 62575 $384,989.00   25-Jul-05   $19,249.45 $11,549.67
16-SR3-305(C) 2005 Chip and Seal Program na Vance Bros. 62421 $157,372.70       $7,868.64 $4,721.18
20-SR4-405(C) 2005 Overlay Program, Phase 2 $700,000.00 LRM Industries   $767,065.55   11-Jul-05   $38,353.28 $23,011.97
21-SR5-405(C) 2005 Overlay and Concrete, Phase 3 na Kansas Heavy 62450 $708,355.33[1] 30-Jun-05 18-Jul-05   $35,417.77 $21,250.66
33-PW1-605(C) Wakarusa Service Center, Master Plan               $0.00 $0.00
51-SI1-1005(C) 2005 Traffic Signal Renovations $300,000.00             $0.00 $0.00
54-SW3-1105(C) Yale Road, West of Iowa Street, Sidewalk na Morgan Concr. 63716 $28,624.00   30-Jan-06      
58-BR1-1105(C) HVAC Reconstruction, 2nd Floor, City Hall                  
Benefit District Projects
    Request           Work Engineering  
    for         P.O. Order Fee Inspection
Project Number Project Name Improve. Amount Consultant Contractor P.O. No. Amount Start Date Estimate Fee
15-CP4-305(BD) Hanscom-Tappan Subdivision public hearing 7-19-05  $    350,000.00 Landplan RD Johnson 63145 $130,099.25 14-Nov-05   $3,902.98
22-GI2-405(BD) 33rd and Nieder Road, Geometric Improvements                  
45-GI5-905(BD) K-10 and O'Connell Road, Left Turn Lane, Geometric Improvements     Peridian            
                     
Private Projects
    Plans Plans     Inspection     Engineering  
    Approved Approved   Amount Fee Inspection Completion Fee Inspection
Project Number Project Name City Eng. Dir. Utilities Contractor Escrowed Amount Fee Rec'd Date Estimate Fee
02-SS1-105(P) Lot 2, Oread West No. 14 (Family Health) 17-Feb-05 16-Feb-05 RD Johnson $9,542.00          
03-ST1-105(P) Lot 2, Oread West No. 14 (Family Health) 20-Jun-05 na              
04-CP1-105(P) N 7th and Elm 14-Mar-05 31-Jan-05              
06-SS2-105(P) Stoneridge North Subdivision 3-May-05 18-Apr-05 McLouth Exc. $271,898.00 $5,922.09 27-Jul-05 12-Jul-05   $5,922.09
07-CP2-105(P)  Stoneridge North Subdivision 28-Jun-05 13-Jun-05 McLouth Exc. $1,044,364.95 $24,143.12 15-Dec-05 6-Dec-05   $24,143.12
08-SS3-205(P) Carpenter Addition No. 2 22-Apr-05 16-Feb-05 J&H Constr. none $390.30 6-Oct-05 26-May-05   $390.30
10-SS4-205(P) Salvation Army 20-Jun-05 16-Feb-05 LRM Indust. $140,000.00          
11-ST2-205(P) Carpenter Addition No. 2                  
13-SS5-205(P) Hanscom-Tappan Subdivision 19-Apr-05 18-Apr-05 Linaweaver $75,998.90 $2,273.07   15-Nov-05   $2,273.07
14-CP3-205(P) Hanscom-Tappan Subdivision 25-May-05   Linaweaver $280,286.15 $7,157.74 6-Sep-06 31-Dec-05   $7,157.74
17-SS6-405(P) Ironwood North Additional sanitary sewer 20-Apr-05 na McLouth Exc. $20,000.00 $495.39 13-Jun-05 18-May-05   $495.39
18-SS7-405(P) Oregon Trail Addition, Sanitary Sewer Improvements   18-Apr-05              
19-CP5-405(P) Oregon Trail Addition, Street, Storm Sewer, Waterline Improvements                  
23-SS8-405(P) Fox Chase South No. 3, Sanitary Sewer Improvements (Lines J,K,L,M) 19-Jan-06 na King's Constr. $95,889.40 $2,804.68 21-Aug-06 31-Jul-06   $2,804.68
24-CP6-405(P) Fox Chase South No. 3, Street, Storm Sewer, Waterline Improvements 19-Jan-06 23-Jan-06              
25-SS9-505(P) Doolittle Subdivision, Sanitary Sewer Improvements 6-Jan-06 na              
26-CP7-505(P) Doolittle Subdivision, Street, Storm Sewer, Waterline Improvements 20-Dec-05 15-Dec-05              
28-SS10-505(P) Family Video (19th and Mass), Sanitary Sewer Improvements 14-Sep-05 na Rockford $15,500.00 $465.00 26-Jan-06 28-Nov-05   $465.00
29-SS11-605(P) Hutton Farms West No. 1, Sanitary Sewer Improvements 1-Aug-05 26-Jul-05 Emery Sapp -- $8,113.80 21-Jun-06 8-Mar-06   $8,113.80
30-CP8-605(P) Hutton Farms West No. 1, Street, Storm Sewer, Waterline Improvements 2-Sep-05 1-Sep-05 Emery Sapp -- $11,156.51 5-Jun-06 22-May-06   $11,156.51
31-GI4-605(P) 1800 Blk of Massachusetts & New Hampshire (Family Video), Geometric Impr. 14-Sep-05 na Rockford $13,134.00 $394.02 26-Jan-06 23-Jan-06   $394.02
32-SS12-605(P) Lake Estates at Alvamar 28-Oct-05 28-Oct-05 Redford Con $189,027.00 $5,670.81 14-Jul-06 1-Mar-06   $5,670.81
34-SW1-605(P) 202 N. 5th Street, Sidewalk, Storm Sewer Improvements 29-Sep-05 26-Sep-05 Lawrenz             
35-ST3-605(P) 4101 W. 6th Street (Lot 1, Free State Veterinary Hospital), Storm Sewer Impr. 23-Aug-05 na              
36-CP9-705(P) Lake Estates at Alvamar, Street, Storm Sewer, Waterline Improvements 28-Oct-05 28-Oct-05 RD Johnson $550,432.00 $14,257.80 14-Jul-06 30-Jun-06 SWPPP issues. $14,257.80
37-CP10-705(P) 8th and New Hampshire (Southeast Corner), Street, Parking Impr. 25-Oct-05 na RD Johnson $35,317.67 $1,028.68 10-Oct-06 12-Jan-06   $1,028.68
38-SS13-805(P) Homewood Gardens Suburban Addition, Sanitary Sewer Improvements 15-Aug-05 na Conley $11,000.00 $330.00 15-Dec-06 17-Oct-05   $330.00
39-SS14-805(P) Habitat Neighborhood Addition No. 5, Sanitary Sewer Improvements 20-Jan-06 na Kings Cons. na $2,102.08 13-Jul-06 29-Jun-06   $2,102.08
40-CP11-805(P) Habitat Neighborhood Addition No. 5, Street, Storm Sewer, Waterline Improvements 20-Jan-06 23-Jan-06 Kings Cons. na $5,690.28 18-Jan-07 25-Jul-06   $5,690.28
41-SS15-805(P) The Cove, Sanitary Sewer Improvements 27-Dec-05 na McLouth Excavating $114,497.50 $3,784.89 30-May-06 16-May-06   $3,784.89
42-CP12-805(P) The Cove, Street, Storm Sewer, Waterline Improvements 19-Jan-06 23-Jan-06 Kings Co, McLouth Excavating $335,485.15 $7,810.76 14-Jul-06 14-Jun-06   $7,810.76
43-SW2-905(P) 700 E. 22nd Street, Sidewalk Improvements and Driveway Closures on Haskell Avenue 13-Oct-05 na Joel Fritzel $8,349.60 $250.49 2-Mar-06 1-Mar-06   $250.49
44-CR2-905(P) 1309 W. 6th Street (McDonald's), Curb and Gutter Improvements 6-Oct-05 na              
46-SS16-905(P) Hutton Farms West No. 2, Sanitary Sewer Improvements 24-Jan-06 na              
47-ST4-905(P) Hutton Farms West No. 2, Storm Sewer and Waterline Improvements                  
48-SS17-1005(P) Sherylville Estates, Sanitary Sewer Improvements 27-Dec-05 22-Dec-05 Kings Cons. $31,530.00 $994.82 Utilities 12-Sep-06   $994.82
49-CP13-1005(P) Sherylville Estates, Storm Sewer and Waterline Improvements 4-Jan-06 3-Jan-06 Kings Cons. $207,042.67 $4,806.05 5-Nov-06 27-Nov-06   $4,806.05
50-SS18-1005(P) Sherylville Estates,  Pump Station No. 35 Improvements na 25-Aug-06 Kings Cons. $26,529.60 $1,482.44 Utilities 28-Nov-06   $1,482.44
52-SS19-1005(P) Fall Creek Farms, 12th Plat, Sanitary Sewer Improvements 12-Dec-05 9-Dec-05 Kings Cons. $24,493.05 $734.79 Utilities 28-Sep-06   $734.79
53-CP14-1005(P) Fall Creek Farms, 12th Plat, Street, Storm Sewer, Waterline Improvements 3-Jan-06 29-Dec-05 Kings Cons. $275,359.75 $7,460.61 26-Dec-06 30-Nov-06   $7,460.61
55-SS20-1105(P) Lot 1, Crossgates No. 3, Sanitary Sewer Extension 12-Dec-05 na McLouth Excavating $31,682.00 $932.76   25-Jan-06   $932.76
56-GI6-1105(P) 31st and Lawrence Avenue, Turn Lane Improvements 28-Jan-06 na RD Johnson $60,000.00 $1,747.88   1-Dec-06   $1,747.88
57-SS21-1105(P) Green Tree Subdivision No. 2, Sanitary Sewer Improvements 23-Dec-05 na McLouth Exc.   -- -- 17-Jan-06   --
59-SW4-1105(P) 201-209 W. 8th Street, Sidewalk and Curb Reconstruction 17-May-06 na Gene Fritzel Construction Co., Inc. $62,025.00          
60-SS22-1105(P) Park West Gardens, Sanitary Sewer Improvements 10-Jan-06 na McLouth Exc. $34,232.50 $1,026.98 25-May-06 12-May-06   $1,026.98
State Projects
                  Engineering  
    State-City   City Share P.O. Start Date Completion    Fee Inspection
Project Number Project Name Shares Contractor P.O. No. Amount   Date   Estimate Fee
01-SR1-105(S) 6th Street, Arkansas to Mass. 50/50 LRM Industries 62364 $433,478.35 6-Jun-05 10-Aug-05    $   16,000.00  $     4,334.78
                     
             Total Engineering/Inspection Fees $153,884.31 $214,396.18

[1]
bsheppard:
Original PO for $695,255.33  Increased $13,100.00 on 11/8/05