| CITY OF LAWRENCE | |||||||||
| City Bid No. 08044 | |||||||||
| Project No. 03-TC1-108(C) -Lawrence Avenue, Harvard Road to 9th Street | |||||||||
| Traffic Calming Improvements | |||||||||
| Bid Date: June 24, 2008 | |||||||||
| Engineer's Estimate: $15,920.00 | |||||||||
| LRM Industries, Inc. | Kansas Heavy Const. | Comet Corporation | |||||||
| ITEM | DESCRIPTION | UNITS | QUANTITY | UNIT PRICE | AMOUNT | UNIT PRICE | AMOUNT | UNIT PRICE | AMOUNT |
| 1 | Mobilization | L.S. | 1 | $ 1,200.00 | $ 1,200.00 | $ 1,500.00 | $ 1,500.00 | $ 296.00 | $ 296.00 |
| 2 | Earthwork | L.S. | 1 | $ 1,100.00 | $ 1,100.00 | $ 550.00 | $ 550.00 | $ 1,110.00 | $ 1,110.00 |
| 3 | Removal of Existing Pavement | L.S. | 1 | $ 2,200.00 | $ 2,200.00 | $ 1,750.00 | $ 1,750.00 | $ 3,330.00 | $ 3,330.00 |
| 4 | Curb and Gutter, Type CG-1 | L.F. | 56 | $ 20.00 | $ 1,120.00 | $ 34.50 | $ 1,932.00 | $ 25.00 | $ 1,400.00 |
| 5 | Aggregate Base (6") (AB-3) | S.Y. | 88 | $ 18.00 | $ 1,584.00 | $ 10.00 | $ 880.00 | $ 29.95 | $ 2,635.60 |
| 6 | Speed Cushion | EACH | 2 | $ 3,300.00 | $ 6,600.00 | $ 4,150.00 | $ 8,300.00 | $ 4,075.00 | $ 8,150.00 |
| 7 | Seeding, Mulching and Fertilizing | L.S. | 1 | $ 600.00 | $ 600.00 | $ 400.00 | $ 400.00 | $ 250.00 | $ 250.00 |
| 8 | Traffic Control | L.S. | 1 | $ 1,300.00 | $ 1,300.00 | $ 1,400.00 | $ 1,400.00 | $ 1,550.00 | $ 1,550.00 |
| GRAND TOTAL | $ 15,704.00 | $ 16,712.00 | $ 18,721.60 | ||||||