On September 16, 2008, the City of Lawrence opened proposals for the following:
Project 04-SI1-208(BD) – City Bid No. B08072
6th & Congressional Traffic Signal and Congressional Traffic Island
|
VENDOR |
TOTAL BID |
|
Engineer’s Estimate (BG Consultants) |
$274,648.00 |
|
Torgeson Electric |
$247,950.40 |
|
J. Warren Co., Inc. |
$259,370.28 |
|
Wildcat Concrete Services, Inc. |
$296,793.90 |
Project Details: The project includes construction of improvements at the intersection of 6th Street and Congressional Drive, including signalization of the intersection and a traffic calming island on Congressional Drive south of 6th Street. The island is proposed to be a raised median approximately 6 feet wide and 21 feet in length containing landscaping.
Project Schedule: Construction will begin this fall after the contract is signed. Depending on weather conditions, this project is expected to be completed within three months after construction begins.
Project Funding: The project is being funded by a benefit district. By resolution, the city-at-large cost for the improvements is five-ninths. Walmart and 6WAK have agreed to cover the City’s cost for improvements in addition to their share, adding up to two-thirds of the project costs. The remaining one-third of the cost will be assessed to the other three corners of the intersection.
Action Request. Approve bid from Torgeson Electric for Project 04-SI1-208(BD), 6th & Congressional Traffic Signal and Congressional Traffic Island in the amount of $247,950.40 provided the contractor can meet the terms established in the contract documents.