| CITY OF LAWRENCE, KANSAS | |||||||||
| PUBLIC WORKS DEPARTMENT | |||||||||
| CONSTRUCTION CONTRACT CHANGE ORDER | |||||||||
| Project Number and Name | 19-CP6-506(BD) & 25-CP8-806(BD) | ||||||||
| Overland & Stonerige Drive | |||||||||
| Change Order No | 1 | Date | 9/23/2008 | ||||||
| Contractor Name & Address | R.D. Johnson | ||||||||
| 1705 N. 1399 Road | |||||||||
| Lawrence, KS 66046 | |||||||||
| The following changes are being made to the referenced construction contract:that are not included in | |||||||||
| the original unit price bid items: | |||||||||
| Item No. | Description | Units | Unit Cost | Quantity (+/-) | Net Change in Contract Price ($) | ||||
| 39A | Single Beam Gaurdrail w/ Reflectors | Ea | $1,600.00 | 1 | $100.00 | ||||
| 120A | Concrete Encasement | LF | $35.00 | 40 | $1,400.00 | ||||
| 121 | 24" MJ Bend 22 1/2 | Ea | $1,221.75 | 2 | $2,443.50 | ||||
| 122 | 24" Megalug Gland | Ea | $222.60 | 5 | $1,113.00 | ||||
| 123 | 16" Megalug Gland | Ea | $133.61 | 5 | $668.05 | ||||
| 124 | 16" MJ Bend 22 1/2 | Ea | $368.00 | 2 | $736.00 | ||||
| 125 | Concrete | CY | $97.15 | 7 | $680.05 | ||||
| 126 | Equipment & Labor | LS | $7,160.00 | 1 | $7,160.00 | ||||
| 127 | Overhead & Profit | LS | $1,985.39 | 1 | $2,746.46 | ||||
| Total | $17,047.06 | ||||||||
| Changes to original unit price bid items are as follows: | |||||||||
| Item No. | Description | Units | Unit Cost | Quantity (+/-) | Net Change in Contract Price ($) | ||||
| 2 | Construction Staking | LS | $7,100.00 | 1 | $700.00 | ||||
| 109 | 16" DIP CL50 | LF | $32.08 | 5 | $160.40 | ||||
| 110 | 24" DIP CL50 | LF | $54.99 | 5 | $274.95 | ||||
| Total | $1,135.35 | ||||||||
| Original Contract Amount | $1,690,649.46 | ||||||||
| Net Change by Previous Change Order(s) | $0.00 | ||||||||
| Net Change by This Change Order | $18,182.41 | ||||||||
| New Contract Amount | $1,708,831.87 | ||||||||
| Approved By: | |||||||||
| Date: | |||||||||
| Contractor | |||||||||
| Date: | |||||||||
| Asst Dir of Public Works | |||||||||