Memorandum

City of Lawrence

Public Works Department

 

TO:

Charles Soules, Public Works Director

FROM:

Shoeb Uddin, City Engineer

CC:

Walt Ward, Lyle Morris, Margene Swarts

Date:

July 27, 2010

RE:

Award of City Bid No. B1042

2009 CDBG Sidewalk Gap Project - City Project No. PW0929

August 03, 2010 City Commission Meeting Agenda Item

 

Introduction

On July 20, 2010 Bid Proposals for “2009 CDBG Sidewalk Gap Program” were opened and read aloud by the City Clerk in accordance to the procurement policies and procedures of the City of Lawrence, Kansas. Following is a summary of the Bid proposals. Attached is the detailed Bid Tab.

 

TOTAL  BID

Engineer’s Estimate

$279,362.50

R.D. Johnson Excavating

$229,076.20

Kansas Heavy Construction

$347,765.00

Love’s Enterprise, Inc.

$395,233.25

 

Project Details / Status

This project consists of installing new sidewalks in the low-mod areas of the city in order to close gaps at various selected locations. Some of the major locations where new sidewalks will be placed include east side of Iowa Street from 23rd to 27th, south side of 23rd Street from Harper to Haskell, west 18th Street from Ohio to Vermont, and Vermont Street from Massachusetts to Montana. The project also includes removal and replacement of the existing broken and unsafe sidewalks along East 13th Street from Connecticut to Haskell. Sidewalk project along East 13th will be coordinated with the upcoming mill and overlay project in this area.

 

Project Schedule

This project is scheduled to begin later this summer and is expected to be completed before the end of the year.

 

Project Funding

 

CDBG Funds

$226,000.00

USD 497

$    6,000.00  (for sidewalk along W. 18th Street between Kentucky  and Vermont)

Total

$232,000.00

 

Bid Evaluation / Recommendation

Staff has evaluated all bid proposals to check for accuracy, completeness and other applicable criteria / requirements. As shown in the Summary Table, the bid proposal from RD Johnson Excavation, Inc. offers the lowest and best total bid price for this project. Staff recommends “Award of City Bid No. B1042” to R. D. Johnson Excavating.

 

Action Request

Award City Bid No. B1042 (for 2009 CDBG Sidewalk Gap Program – PW0929) to R.D. Johnson Excavating in the amount of $229,076.20 and authorize City Manager to sign the Construction Contract for this project.

 

Attachments

Project Location Map

Bid Tab