| Lawrence Taxiway C Reconstruction | ||||||||||
| Estimate | ||||||||||
| ITEM | DESCRIPTION | UNIT | QUANTITY | UNIT PRICE IN FIGURES | AMOUNT IN FIGURES | |||||
| 1 | Mobilization | L.S. | 1 | $20,000.00 | $20,000.00 | |||||
| 2 | Contractor Construction Staking | L.S. | 1 | $10,000.00 | $10,000.00 | |||||
| 3 | Demolition | L.S. | 1 | $15,000.00 | $15,000.00 | |||||
| 4 | Unclassified Excavation | Cu. Yd. | 500 | $15.00 | $7,500.00 | |||||
| 5 | Embankment In Place | Cu. Yd. | 500 | $10.00 | $5,000.00 | |||||
| 6 | Crushed Aggregate Base Course (6") | Sq. Yd. | 1,800 | $12.00 | $21,600.00 | |||||
| 7 | Bituminous Pavement | Ton | 600 | $100.00 | $60,000.00 | |||||
| 8 | Pavement Marking | L.S. | 1 | $10,000.00 | $10,000.00 | |||||
| 9 | Seeding | M.S.F. | 20.0 | $100.00 | $2,000.00 | |||||
| 10 | Mulching | M.S.F. | 20.0 | $100.00 | $2,000.00 | |||||
| PAVING TOTAL | $153,100.00 | |||||||||
| 15 PERCENT CONTINGENCY | $22,965.00 | |||||||||
| TOTAL PROJECT COST | $176,065.00 | |||||||||
| 11 | Survey | $ 4,000.00 | ||||||||
| 12 | Geotech Report | $ 6,000.00 | ||||||||
| 13 | Engineering | $ 15,000.00 | ||||||||
| 14 | Inspection | $ 10,000.00 | ||||||||
| DESIGN TOTAL | $ 35,000.00 | |||||||||
| PROJECT GRAND TOTAL | $211,065.00 | |||||||||