| Lawrence West Apron Reconstruction | |||||||
| Estimate | |||||||
| ITEM | DESCRIPTION | UNIT | QUANTITY | UNIT PRICE IN FIGURES | AMOUNT IN FIGURES | ||
| 1 | Mobilization | L.S. | 1 | $20,000.00 | $20,000.00 | ||
| 2 | Contractor Construction Staking | L.S. | 1 | $10,000.00 | $12,000.00 | ||
| 3 | Demolition | L.S. | 1 | $20,000.00 | $20,000.00 | ||
| 4 | Unclassified Excavation | Cu. Yd. | 1,000 | $15.00 | $15,000.00 | ||
| 5 | Embankment In Place | Cu. Yd. | 1,000 | $10.00 | $10,000.00 | ||
| 6 | Crushed Aggregate Base Course (6") | Sq. Yd. | 5,200 | $10.00 | $52,000.00 | ||
| 7 | Bituminous Pavement | Ton | 1,500 | $100.00 | $150,000.00 | ||
| 8 | Pavement Marking | L.S. | 1 | $5,000.00 | $5,000.00 | ||
| 8 | Trench drain materials | L.S. | 1 | $32,000.00 | $32,000.00 | ||
| 9 | Safety Barricades | L.S. | 1 | $2,000.00 | $2,000.00 | ||
| 10 | Seeding | M.S.F. | 5.0 | $100.00 | $500.00 | ||
| 11 | Mulching | M.S.F. | 5.0 | $100.00 | $500.00 | ||
| PAVING TOTAL | $319,000.00 | ||||||
| 15 PERCENT CONTINGENCY | $47,850.00 | ||||||
| TOTAL PROJECT COST | $366,850.00 | ||||||
| 12 | Survey | $ 6,000.00 | |||||
| 13 | Geotech Report | $ 6,000.00 | |||||
| 14 | Engineering | $ 35,000.00 | |||||
| 15 | Inspection | $ 20,000.00 | |||||
| DESIGN TOTAL | $ 67,000.00 | ||||||
| PROJECT GRAND TOTAL | $433,850.00 | ||||||