BUILDINGS AND STRUCTURES
Recommened capital planning for facilities
Priority
In Progress
  Completed                total 
Buildings and projects  Total Costs  Year requested  2015   2016   2017   2018   2019   2020   by project 
                 $                -  
Fire/Med #1 746 Kentucky St.                  
Total Remodel - does not include DCSC  ?               
Plumbing replacement                $                -  
HVAC and Controls replacement   2011              $                -  
Electrical upgrade   2011              $                -  
Concrete repairs                  $                -  
                 $                -  
Fire/Med #2  2128 Harper St.                  
concrete repair  $           14,000 2014              $                -  
concrete replacement  $          300,000 2014              $                -  
                 $                -  
Fire/Med #3  3708 W. 6th St.                  
concrete repair  $           17,000 2014              $                -  
concrete replacement  $          170,000 2014              $                -  
HVAC equipment  $           50,000 2013        $       50,000      $          50,000
Roof replacement  $          140,000 2014    $        140,000          $        140,000
                 $                -  
Fire/Med #4  2121 Wakarusa Dr.                  
concrete repair  $           46,000 2014              $                -  
concrete replacement  $          300,000 2014              $                -  
    2014              $                -  
Fire/Med #5  1911 Stewart Ave.                  
concrete repair  $           17,000 2014              $                -  
concrete replacement  $          395,000 2014              $                -  
water infiltration in dorm area  $           18,000 2015    $          18,000          $          18,000
Drainage and sidewalk repairs east side  $           50,000 2013    $          50,000          $          50,000
                 $                -  
Fire/Med Investigation Center  1839 Massachusetts St.                  
concrete repair                $                -  
concrete replacement                $                -  
                 $                -  
Fire/Med Training Center 1941 Haskell Ave.                  
concrete repair  $           66,000 2014              $                -  
concrete replacement  $          570,000 2014              $                -  
                 $                -  
Fire/Med Stone Barn Terrace                  
concrete repair                $                -  
concrete replacement                $                -  
                 $                -  
Art Center  940 New Hampshire St.                  
Guttering repairs
Res 7080
 $             5,000 2012  $            5,000            $            5,000
roof repairs
Res 7080
 $           10,000 2012  $          10,000            $          10,000
roof replacement  $          250,000        $     250,000      $        250,000
                 $                -  
Paint metal
Res 7080
 $           20,000 2012  $          10,000      $       10,000      $          20,000
Investigation & Training Center  4820 Bob Billings Parkway                  
Exterior repairs  $          400,000 2010          $     400,000    $        400,000
HVAC equipment  $           80,000 2010        $       80,000      $          80,000
                 $                -  
Downtown  Lawrence                  
Lighting replacement  $          200,000 2010  $        100,000      $     100,000      $        200,000
Pole replacement  $           90,000 2011      $          90,000        $          90,000
Canopy lighting/Maintenance  $           85,000 2013      $          75,000    $       10,000    $          85,000
                 $                -  
Parking Lot #2  749 New Hampshire Street                  
                 $                -  
Parking Lot #3  850 Vermont Street                  
                 $                -  
Parking Lot #4  825 New Hampshire St.                  
Patch,Microsurface,Striping 3155sqft  $           25,000              $                -  
Parking Lot #5   924 Vermont Street                  
Patch,Microsurface,Striping 2980sqft  $           24,000              $                -  
Parking Lot #7   195 W 11th St.                  
Patch,Microsurface,Striping 2320sqft  $           19,000              $                -  
Parking Lot #8   875 Rhode Island Street                  
Patch,Microsurface,Striping 4120sqft  $           17,000              $                -  
Parking Lot #9   975 Vermont Street                  
Patch,Microsurface,Striping 1435sqft  $           12,000              $                -  
Parking Lot #10  1024 Vermont Street                  
                 $                -  
Parking Lot #11  Vermont Street                  
                 $                -  
Parking Lot #12  700 Vermont                  
                 $                -  
Parking Lot #14   798 Vermont Street                  
Patch,Microsurface,Striping 1410sqft  $           11,000              $                -  
Parking Lot #15   601 Vermont                  
Patch,Microsurface,Striping 1150sqft  $             9,000              $                -  
Parking Lot #16   611 Rhode Island                  
Patch,Microsurface,Striping 1400sqft  $           11,000              $                -  
Parking Lot #17  East 6th Street                  
                 $                -  
Parking Lot #18                  
Patch,Microsurface,Striping 4315sqft  $           34,520              $                -  
Parking Lot North Lawrence                  
                 $                -  
Community Health Building                  
Boiler replacement  $          200,000 2012    $        200,000          $        200,000
Access system replacement/update  $           65,000 2012              $                -  
Parking Lot, resurface  $          200,000 2012      $        200,000        $        200,000
Roof    $          400,000 2012      $        400,000        $        400,000
Generator replacement  $           80,000 2013      $          80,000        $          80,000
Chiller replacement  $          150,000 2013    $        150,000          $        150,000
building Stabilization  $           20,000 2015    $          20,000          $          20,000
City Hall  6 East 6th Street                    
HVAC unit replacement/cc heat
Res 7080
 $          590,000 2012  $        195,000    $          40,000        $        235,000
Digital control upgrade
Res 7080
 $          200,000 2012  $        200,000            $        200,000
carpet & hearing loop in commission room  $           20,000 2014      $          10,000  $       10,000      $          20,000
Carpet remaining floors  $           40,000              
Concrete repairs  $           30,000 2014    $          30,000          $          30,000
Atrium glass  $           50,000              $                -  
Windows  $          200,000 2011    $        500,000          $        500,000
shade for atium  $          200,000              $                -  
seal brick  $           80,000 2013              $                -  
Riverfront Parking Garage  Riverfront Plaza                  
Security cameras  $           70,000 2014              $                -  
Electrical service replacement
Res 7080
 $           50,000 2014  $          50,000            $          50,000
                 $                -  
Seal electrical room  $           15,000 2013    $          15,000          $          15,000
concrete replacement on ramp  $           30,000 2013    $          30,000          $          30,000
Painting  $           25,000 2013    $          25,000          $          25,000
New Hampshire Parking Garage  933 New Hampshire Street                  
                 $                -  
Lighting upgrade  $           50,000              $                -  
Elevator enclosurer  $           30,000 2011  $          30,000            $          30,000
Security cameras  $           70,000              $                -  
                 $                -  
Vermont Street Parking Garage 727 Vermont                $                -  
HVAC for shop/office  $             8,000  $            8,000            $            8,000
Security Cameras  $           70,000              $                -  
Traffic Building  445 Mississippi Street                  
Generator  $           60,000 2012          $       60,000    $          60,000
Roof replacement  $           80,000 2013          $       80,000    $          80,000
Heat replacement
Res 7080
 $           20,000 2013  $          20,000            $          20,000
Remodel  $          100,000 2014      $        100,000        $        100,000
Senior Center  745 Vermont Street                  
Screening emergency stairs  $             6,000              $                -  
concrete replacement  $           25,000 2012    $          25,000          $          25,000
Airconditioning replacement  $           60,000 2010    $          60,000          $          60,000
Fiber installtion  $           10,000 2015              $                -  
Boiler replacement  $          100,000 2013              
Window replacement  $          200,000 2013              
Replace gym wood flooring  $          200,000 2014              
Plumbing replacement  $          400,000              $                -  
HVAC and Controls replacement  $       1,000,000              $                -  
Seal and tuck point   $          180,000 2013    $        180,000          $        180,000
Electrical upgrade  $          500,000              $                -  
Elevator rehabilitation  $           70,000 2015    $          70,000          $          70,000
General repairs and upgrades  $       3,000,000              $                -  
Solid Waste  1140 Haskell                   
Roof  $           20,000 2013              $                -  
window replacement  $             5,000 2009              $                -  
Remodel for traffic operations  $          100,000              $                -  
Structural Settling repairs  $           40,000 2013              $                -  
Airport  1930 N Airport Road                  
Airconditioning replacement  $           10,000              $                -  
West appron overlay  $          100,000 2014              $                -  
insulate shop/Improvement  $           30,000 2012              $                -  
Wildlife fence city share  $          100,000 2015    $        100,000          $        100,000
Pavement Maintenance  $          100,000 2009              $                -  
Upgrade lighting  $           20,000 2012              $                -  
Street  1128  Haskell                  
fiber
Res 7080
 $           30,000 2014  $          30,000            $          30,000
install shower in Mens RR  $           20,000 2014      $          20,000        $          20,000
Windows  $             5,000              $                -  
Exterior lighting  $           10,000 2012      $          10,000        $          10,000
Red Barn Replacement  $          500,000 2014        $     500,000      $        500,000
salt dome roof west 40  $          150,000 2013    $        150,000          $        150,000
                 $                -  
Maintenance Garage  1141 Haskell                  
Overhead heaters  $           30,000 2012    $          30,000          $          30,000
Upgrade lighting  $           20,000 2012    $          20,000          $          20,000
furnace  $           10,000 2013    $          10,000          $          10,000
                     $                -  
                 $                -  
                     
Totals by year  $     13,709,520    $        658,000  $     1,823,000  $     1,025,000  $  1,000,000  $     550,000  $             -    $     5,056,000