CITY COMMISSION AGENDA ITEM |
|
|
Department: |
Parks and Recreation |
Commission Meeting Date: May 15, 2018 |
||||||||
|
Staff Contact: |
Mark Hecker, Assistant Director Parks and Recreation |
|||||||||
|
Recommendations/Options/Action Requested: |
|
|||||||||
|
Award Bid No. B1819 – Lawrence Indoor Aquatic Center Pool painting (CIP #PR821) to J.F. McGivern, Inc. in the amount of $111,430.00. |
|
|||||||||
|
Executive Summary: |
The Lawrence Indoor Aquatic Center pool painting project (PR1821CIP) was approved for funding by the City Commission, as part of the City’s 2018 Budget and CIP. This project will provide sandblasting of all painted pool surfaces and the reapplication of new epoxy, primer and paint. Work is scheduled to be completed during the facilities annual maintenance shutdown in August. The City received two proposals with J.F. McGivern, Inc. providing the low bid and meeting all the specifications.
|
|||||||||
|
Strategic Plan Critical Success Factor |
Innovative Infrastructure and Asset Management |
|||||||||
|
Fiscal Impact (Amount/Source): |
The total fiscal impact to the City will be $111,430.00. The original project estimate of $110,000. Sufficient expenditure authority exists in the 2018 Parks & Recreation General Fund Budget to fund the additional $1,430. |
|||||||||
|
Attachments: |
||||||||||
|
Reviewed By: (for CMO use only) |
☐TM ☐DS ☐CT ☒BM |