To: Mike Wildgen
City Manager
From: Debbie Van Saun
Asst. City Manager
Re: agenda items
Date: July 6, 2005
Please place the following item on the City Commission agenda for consideration at their July 12, 2005 meeting:
Bids for Airport Improvement Project:
We opened bids on May 24th for the partial parallel taxiway improvement/lighting system installation project at the Lawrence Municipal Airport (Schedule I and II, respectively). A summary of bids for Schedule I of this project and comparison with the engineer’s estimate is detailed below.
Project Background
The construction of a partial parallel taxiway to runway 1-19 and lighting system improvements is a capital improvement project that is in the City’s Capital Improvement Budget as well as the airport’s master plan. This project will insure the first phase of providing safe access to runway 1-19 and improve the lighting systems to runway 15-33 and taxiway A.
Project Funding
This project is eligible for federal grant funding via FAA entitlement and discretionary funds. An FAA grant will fund 95% and the City will be responsible for 5%. Bonding authority for this project was established via Resolution 6311, adopted by the City Commission May 2, 2001 for this and other previously completed airport improvement projects.
Project Status
As noted in the attached letter from ADG, the City’s engineering consultant for the project, the one bid that was received for Schedule I (construction of partial parallel taxiway) was significantly over the engineer’s estimate:
Engineer’s Estimate $575,348.00
Hamm, Inc. bid 753,009.11
Due to the lack of acceptable bids and the fact that available FAA funding for this project will not be sufficient to award this Schedule, the engineer is recommending that the Schedule I bid should be rejected and that the work should be re-bid for construction in 2006. FAA is in agreement with this recommendation and course of action
Commission Action
Approval is requested from the City Commission to authorize the rejection of the bid received for Schedule I of the Airport Improvement Project No. 3-20-0047-12 and that a new bid date be set for this project at a yet to be determined date in 2006.
Please let me know if you have any questions.
c: Dave Corliss, Asst. City Manager
Ed Mullins, Finance Director
Alan Landis, Purchasing Manager
Chuck Soules, Public Works Director
Aviation Advisory Board
att.